Hawk Construction: TxDOT Bid Results and Margins

Name as published by TxDOT: HAWK CONSTRUCTION · Data as published by TxDOT, lettings Oct 14, 2025 to Aug 5, 2026, retrieved Nov 24, 2026.

Proposals bid
10
Low bids (rank 1)
1
Win rate
10%
Low-bid value
$1.5M
Money left on table
$415K
Avg. bid vs. estimate
+25.44%

From Oct 14, 2025 to Aug 5, 2026, Hawk Construction submitted 10 bids on TxDOT proposals and was the apparent low bidder on 1 of them (10%), with low bids totalling $1,469,600. In 1 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $414,717 (28.22% of those bids); the median gap was 28.22%. On average its bids came in 25.44% above TxDOT's engineer's estimate. Its most frequent district was El Paso (10 bids).

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

By year

YearBidsLow bidsWin rateLow-bid value
20254125.0%$1,469,600
2026600.0%$0

Head-to-head rivals

BidderProposals togetherRanked ahead
Synergy Project Contractors, Inc.81 of 8
International Eagle Enterprises, Inc.73 of 7
Premier Contractors LLC30 of 3
Dan Williams Company20 of 2
Horizone Construction I, Ltd20 of 2
Icos Management, LLC21 of 2
O. Trevino Construction, LLC20 of 2
Scr Civil Construction, LLC20 of 2

Districts and work types

DistrictBids
El Paso10
Work type of low bidsLow bids
Routine Maintenance Project1

Recent bids

Let dateProposalCountyWork typeRankBid totalvs. low bidvs. estimate
2026-08-056504-80-001El PasoRoutine Maintenance Project5 of 6$2,555,000+44.2%+5.1%
2026-06-020924-00-162El PasoBridge Maintenance3 of 6$1,075,146+32.3%+39.8%
2026-05-070167-02-092El PasoSafety Improvement Projects3 of 3$3,319,132+33.9%+10.5%
2026-05-056498-81-001El PasoRoutine Maintenance Project3 of 3$2,315,950+40.3%+131.9%
2026-04-080674-01-083El PasoPedestrian, Sidewalks & Curb Ramps5 of 6$1,580,000+26.5%+20.8%
2026-03-046493-40-001El PasoBridge Preventative Maintenance9 of 10$1,684,407+64.3%+30.5%
2025-12-116489-59-001El PasoRoutine Maintenance Project3 of 3$879,870+1.1%-4.2%
2025-12-096463-91-001El PasoBridge Preventative Maintenance - Sealed5 of 7$857,041+54.2%-0.5%
2025-12-036489-56-001El PasoRoutine Maintenance Project1 of 3$1,469,600—-3.2%
2025-10-146484-69-001El PasoRoutine Maintenance Project3 of 3$1,229,875+42.4%+23.6%

Report an error. Wrong company merged, a name change, or a figure that does not match TxDOT's file? Email bidtabulation@apps.adeptaoperations.com. We respond within five business days. See how corrections work.

Compare your own unit prices with TxDOT history: benchmark a bid tab.