Skip to content
BidTabulation.comDOT bid tabulations & unit-price intelligence
Menu

Crackseal of Texas, LLC: TxDOT Bid Results and Margins

Name as published by TxDOT: CRACKSEAL OF TEXAS, LLC · Data as published by TxDOT, lettings Nov 13, 2024 to Oct 8, 2026, retrieved Nov 24, 2026.

Proposals bid
110
Low bids (rank 1)
21
Win rate
19.09%
Low-bid value
$12.9M
Money left on table
$2.6M
Avg. bid vs. estimate
+45%

From Nov 13, 2024 to Oct 8, 2026, Crackseal of Texas, LLC submitted 110 bids on TxDOT proposals and was the apparent low bidder on 21 of them (19.09%), with low bids totalling $12,924,282. In 21 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $2,617,174 (20.25% of those bids); the median gap was 13.43%. On average its bids came in 45% above TxDOT's engineer's estimate. Its most frequent district was San Antonio (13 bids).

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

By year

YearBidsLow bidsWin rateLow-bid value
20243133.3%$1,232,490
2025401230.0%$7,814,188
202667811.9%$3,877,604

Head-to-head rivals

BidderProposals togetherRanked ahead
D & M Contractors, LLC8535 of 85
Fyl Enterprises, LLC5720 of 57
Greenpak Solutions, Limited Liability Company4216 of 42
Icos Management, LLC2413 of 24
Blacksmith Ventures LLC216 of 21
Scout 5 Construction LLC172 of 17
Garret Shields Infrastructure133 of 13
Scr Civil Construction, LLC82 of 8

Districts and work types

DistrictBids
San Antonio13
Corpus Christi11
Yoakum11
Austin9
Dallas8
Work type of low bidsLow bids
Routine Maintenance Project - Sealed15
Routine Maintenance Project4
Bridge Preventative Maintenance - Sealed2

Closest second-place finishes

Let dateProposalCountyLow bidderLow bidThis bidvs. low bid
2026-10-086509-34-001ColoradoRow Contractors LLC$299,875$307,500+2.5%
2026-09-246504-28-001HaleGreenpak Solutions, Limited Liability Company$465,946$477,955+2.6%
2025-05-066464-83-001GonzalesBk Field Operations LLC$388,629$402,277+3.5%
2026-09-296499-80-001AransasFyl Enterprises, LLC$264,045$276,349+4.7%
2026-07-296501-67-001MedinaScout 5 Construction LLC$271,090$285,687+5.4%

Recent bids

Let dateProposalCountyWork typeRankBid totalvs. low bidvs. estimate
2026-10-086508-46-001ChildressRoutine Maintenance Project - Sealed1 of 3$792,701—-17.2%
2026-10-086509-34-001ColoradoRoutine Maintenance Project2 of 6$307,500+2.5%-5.7%
2026-10-016502-82-001Tom GreenRoutine Maintenance Project - Sealed3 of 6$772,269+5.6%-12.5%
2026-09-296499-77-001NuecesRoutine Maintenance Project - Sealed3 of 5$265,697+34%+51.3%
2026-09-296499-80-001AransasRoutine Maintenance Project - Sealed2 of 5$276,349+4.7%+0.5%
2026-09-246504-26-001TerryRoutine Maintenance Project - Sealed3 of 4$448,043+18.6%-5%
2026-09-246504-27-001LambRoutine Maintenance Project - Sealed1 of 4$715,655—-10.6%
2026-09-246504-28-001HaleRoutine Maintenance Project - Sealed2 of 4$477,955+2.6%-5.4%
2026-09-236508-03-001PanolaRoutine Maintenance Project3 of 4$690,000+26.1%+5.9%
2026-09-176505-02-001HopkinsRoutine Maintenance Project - Sealed6 of 6$323,423+276.5%+147%
2026-09-176506-17-001HuntRoutine Maintenance Project - Sealed5 of 5$353,814+226.8%+50.3%
2026-09-176506-28-001LamarRoutine Maintenance Project - Sealed3 of 3$693,662+122.3%+37.7%

Report an error. Wrong company merged, a name change, or a figure that does not match TxDOT's file? Email bidtabulation@apps.adeptaoperations.com. We respond within five business days. See how corrections work.

Compare your own unit prices with TxDOT history: benchmark a bid tab.