Bontke Brothers Construction Company: TxDOT Bid Results and Margins
Name as published by TxDOT: BONTKE BROTHERS CONSTRUCTION COMPANY · Data as published by TxDOT, lettings Nov 6, 2024 to Jul 2, 2026, retrieved Nov 24, 2026.
- Proposals bid
- 8
- Low bids (rank 1)
- 0
- Win rate
- 0%
- Low-bid value
- $0.000
- Money left on table
- —
- Avg. bid vs. estimate
- +5.49%
From Nov 6, 2024 to Jul 2, 2026, Bontke Brothers Construction Company submitted 8 bids on TxDOT proposals and was the apparent low bidder on 0 of them (0%), with low bids totalling $0. On average its bids came in 5.49% above TxDOT's engineer's estimate. Its most frequent district was Abilene (8 bids).
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
By year
| Year | Bids | Low bids | Win rate | Low-bid value |
|---|---|---|---|---|
| 2024 | 1 | 0 | 0.0% | $0 |
| 2025 | 6 | 0 | 0.0% | $0 |
| 2026 | 1 | 0 | 0.0% | $0 |
Head-to-head rivals
| Bidder | Proposals together | Ranked ahead |
|---|---|---|
| Ck Newberry, LLC | 6 | 1 of 6 |
| J. H. Strain & Sons, Inc. | 6 | 0 of 6 |
| Grey Sky Construction LLC | 4 | 4 of 4 |
| Reece Albert, Inc. | 3 | 0 of 3 |
| Stx Civil | 3 | 0 of 3 |
| A. L. Helmcamp, Inc. | 2 | 0 of 2 |
| Rk Hall, LLC | 2 | 0 of 2 |
| 3lw Civil LLC | 1 | 0 of 1 |
Districts and work types
| District | Bids |
|---|---|
| Abilene | 8 |
Recent bids
| Let date | Proposal | County | Work type | Rank | Bid total | vs. low bid | vs. estimate |
|---|---|---|---|---|---|---|---|
| 2026-07-02 | 2270-01-029 | Taylor | Bicycle Infrastructure Improvements | 6 of 7 | $373,248 | +46.7% | +17% |
| 2025-11-05 | 0069-01-062 | Howard | Overlay | 5 of 5 | $3,412,489 | +68.4% | +22.9% |
| 2025-07-01 | 0181-01-067 | Taylor | Pedestrian, Sidewalks & Curb Ramps | 3 of 5 | $4,686,027 | +12.4% | +14.4% |
| 2025-05-02 | 0181-01-069 | Taylor | Super-2 Highway | 7 of 8 | $12,464,352 | +17.5% | -7.8% |
| 2025-04-04 | 0006-03-149 | Nolan | Overlay | 4 of 5 | $872,001 | +31.2% | -10.2% |
| 2025-04-03 | 0663-03-031 | Taylor | Widen Non-Freeway | 4 of 6 | $3,585,233 | +13.2% | -1.1% |
| 2025-03-05 | 1070-02-010 | Taylor | Widen Non-Freeway | 3 of 6 | $2,512,502 | +40.8% | +6.5% |
| 2024-11-06 | 2033-01-013 | Nolan | Widen Non-Freeway | 5 of 5 | $10,679,710 | +35.3% | +2.2% |
Report an error. Wrong company merged, a name change, or a figure that does not match TxDOT's file? Email bidtabulation@apps.adeptaoperations.com. We respond within five business days. See how corrections work.