Thermoplastic, Standard-Open Graded Asphalt Surfaces, White, Skip, 12"- Approach TO Toll Plaza OR 3-9 Lane Drop (Item 0711 15133): FDOT Unit Price History
12 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure GM
- Weighted average (12 mo)
- $5,513.57/GM
- Contracts (12 mo)
- 12
- Total quantity (12 mo)
- 5.92 GM
- Total amount (12 mo)
- $32,662
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 10 | $5,662.00 | 3.79 | $21,476 |
| 2025 | 2025-01-01 – 2025-12-31 | 17 | $5,471.35 | 8.71 | $47,628 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 12 | $5,513.57 | 5.92 | $32,662 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 05 | 1 | $7,900.00 | +43.3% | 0.34 |
| 06 | 1 | $5,700.00 | +3.4% | 0.06 |
| 07 | 3 | $7,047.68 | +27.8% | 0.81 |
| 08 | 2 | $3,794.11 | -31.2% | 0.51 |
| 10 | 1 | $5,131.63 | -6.9% | 0.25 |
| 12 | 4 | $5,238.56 | -5% | 3.96 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0711 15133 (Thermoplastic, Standard-Open Graded Asphalt Surfaces, White, Skip, 12"- Approach TO Toll Plaza OR 3-9 Lane Drop) is measured in GM. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 12 contracts with a quantity-weighted average of $5,513.57 per GM, on 5.92 GM worth $32,662 in total.
The same report run for earlier periods shows $5,662.00 in 2024 (10 contracts, 3.79 GM), $5,471.35 in 2025 (17 contracts, 8.71 GM), $5,513.57 in the latest 12 months (12 contracts, 5.92 GM). Across those periods the weighted average stayed within three percent.
Quantity let statewide grew 56% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 6 of FDOT's 14 market areas reported this item: area 05 at $7,900.00 (1 contract), area 06 at $5,700.00 (1 contract), area 07 at $7,047.68 (3 contracts), area 08 at $3,794.11 (2 contracts), area 10 at $5,131.63 (1 contract), area 12 at $5,238.56 (4 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0711: 0711 16201 Thermoplastic, Standard-Other Surfaces, Yellow, Solid, 6" ($5,264.57 per GM, 204 contracts); 0711 16101 Thermoplastic, Standard-Other Surfaces, White, Solid, 6" ($5,320.58 per GM, 202 contracts); 0711 11125 Thermoplastic, Standard, White, Solid, 24" FOR Stop Line AND Crosswalk ($7.00 per LF, 188 contracts); 0711 11170 Thermoplastic, Standard, White, Arrow ($86.63 per EA, 181 contracts); 0711 11124 Thermoplastic, Standard, White, Solid, 18" FOR Diagonals AND Chevrons ($5.52 per LF, 165 contracts).
Related items in section 0711
- 0711 16201 · Thermoplastic, Standard-Other Surfaces, Yellow, Solid, 6" ($5,264.57/GM)
- 0711 16101 · Thermoplastic, Standard-Other Surfaces, White, Solid, 6" ($5,320.58/GM)
- 0711 11125 · Thermoplastic, Standard, White, Solid, 24" FOR Stop Line AND Crosswalk ($7.00/LF)
- 0711 11170 · Thermoplastic, Standard, White, Arrow ($86.63/EA)
- 0711 11124 · Thermoplastic, Standard, White, Solid, 18" FOR Diagonals AND Chevrons ($5.52/LF)
- 0711 11123 · Thermoplastic, Standard, White, Solid, 12" FOR Crosswalk AND Roundabout ($3.76/LF)
- 0711 11224 · Thermoplastic, Standard, Yellow, Solid, 18" FOR Diagonal OR Chevron ($5.06/LF)
- 0711 11160 · Thermoplastic, Standard, White, Message OR Symbol ($177.80/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.