Thermoplastic, Standard, White, Solid, 24" FOR Stop Line AND Crosswalk (Item 0711 11125): FDOT Unit Price History

188 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF

Weighted average (12 mo)
$7.00/LF
Contracts (12 mo)
188
Total quantity (12 mo)
129,904 LF
Total amount (12 mo)
$908,982

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-31245$7.85165,395$1,298,043
20252025-01-01 – 2025-12-31232$7.66150,040$1,148,690
Latest 12 months2025-11-01 – 2026-10-31188$7.00129,904$908,982

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
0111$8.07+15.3%7,377
029$7.57+8.1%3,670
0311$7.87+12.4%5,812
0414$9.23+31.9%7,278
0518$7.45+6.4%12,136
0616$6.97-0.4%14,110
0719$6.40-8.6%13,460
0841$7.000%34,215
094$6.61-5.6%4,416
1014$7.28+4%7,231
112$6.32-9.7%2,100
1214$5.78-17.4%7,492
1314$5.25-25%10,425
141$6.62-5.4%182

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0711 11125 (Thermoplastic, Standard, White, Solid, 24" FOR Stop Line AND Crosswalk) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 188 contracts with a quantity-weighted average of $7.00 per LF, on 129,904 LF worth $908,982 in total.

The same report run for earlier periods shows $7.85 in 2024 (245 contracts, 165,395 LF), $7.66 in 2025 (232 contracts, 150,040 LF), $7.00 in the latest 12 months (188 contracts, 129,904 LF). From 2024 to the latest 12 months the weighted average fell 10.8%.

Quantity let statewide shrank 21% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

FDOT's market-area reports for the same 12 months show how location moves the price. Among the 12 market areas with at least three contracts, market area 13 had the lowest weighted average ($5.25 per LF, 14 contracts) and market area 04 the highest ($9.23, 14 contracts), 1.8 times as much. Market area 08 let the most contracts with this item (41). 14 of FDOT's 14 market areas reported the item in this window.

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0711: 0711 16201 Thermoplastic, Standard-Other Surfaces, Yellow, Solid, 6" ($5,264.57 per GM, 204 contracts); 0711 16101 Thermoplastic, Standard-Other Surfaces, White, Solid, 6" ($5,320.58 per GM, 202 contracts); 0711 11170 Thermoplastic, Standard, White, Arrow ($86.63 per EA, 181 contracts); 0711 11124 Thermoplastic, Standard, White, Solid, 18" FOR Diagonals AND Chevrons ($5.52 per LF, 165 contracts); 0711 11123 Thermoplastic, Standard, White, Solid, 12" FOR Crosswalk AND Roundabout ($3.76 per LF, 158 contracts).

Related items in section 0711

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.