Thermoplastic, Preformed, 12" White ON Asphalt Pavement, Railroad Dynamic Envelope (Item 0711 14193): FDOT Unit Price History

16 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF

Weighted average (12 mo)
$11.96/LF
Contracts (12 mo)
16
Total quantity (12 mo)
13,017 LF
Total amount (12 mo)
$155,648

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-3123$14.5914,573$212,659
20252025-01-01 – 2025-12-3117$11.0811,420$126,500
Latest 12 months2025-11-01 – 2026-10-3116$11.9613,017$155,648

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
012$7.36-38.5%1,016
023$7.26-39.3%1,125
041$15.00+25.4%357
051$15.00+25.4%739
062$12.23+2.3%1,102
072$13.51+13%1,113
082$10.67-10.8%1,668
091$10.00-16.4%633
132$13.47+12.6%5,264

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0711 14193 (Thermoplastic, Preformed, 12" White ON Asphalt Pavement, Railroad Dynamic Envelope) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 16 contracts with a quantity-weighted average of $11.96 per LF, on 13,017 LF worth $155,648 in total.

The same report run for earlier periods shows $14.59 in 2024 (23 contracts, 14,573 LF), $11.08 in 2025 (17 contracts, 11,420 LF), $11.96 in the latest 12 months (16 contracts, 13,017 LF). From 2024 to the latest 12 months the weighted average fell 18.0%.

In the same 12 months, 9 of FDOT's 14 market areas reported this item: area 01 at $7.36 (2 contracts), area 02 at $7.26 (3 contracts), area 04 at $15.00 (1 contract), area 05 at $15.00 (1 contract), area 06 at $12.23 (2 contracts), area 07 at $13.51 (2 contracts), area 08 at $10.67 (2 contracts), area 09 at $10.00 (1 contract), area 13 at $13.47 (2 contracts).

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0711: 0711 16201 Thermoplastic, Standard-Other Surfaces, Yellow, Solid, 6" ($5,264.57 per GM, 204 contracts); 0711 16101 Thermoplastic, Standard-Other Surfaces, White, Solid, 6" ($5,320.58 per GM, 202 contracts); 0711 11125 Thermoplastic, Standard, White, Solid, 24" FOR Stop Line AND Crosswalk ($7.00 per LF, 188 contracts); 0711 11170 Thermoplastic, Standard, White, Arrow ($86.63 per EA, 181 contracts); 0711 11124 Thermoplastic, Standard, White, Solid, 18" FOR Diagonals AND Chevrons ($5.52 per LF, 165 contracts).

Related items in section 0711