Delineator, NON-Flexible (Item 0705 11 2): FDOT Unit Price History
18 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $88.98/EA
- Contracts (12 mo)
- 18
- Total quantity (12 mo)
- 1,503 EA
- Total amount (12 mo)
- $133,741
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 20 | $101.74 | 841 | $85,560 |
| 2025 | 2025-01-01 – 2025-12-31 | 23 | $109.83 | 1,574 | $172,878 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 18 | $88.98 | 1,503 | $133,741 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 1 | $85.60 | -3.8% | 19 |
| 03 | 1 | $63.74 | -28.4% | 136 |
| 04 | 3 | $63.98 | -28.1% | 208 |
| 05 | 4 | $87.00 | -2.2% | 444 |
| 06 | 2 | $95.75 | +7.6% | 191 |
| 07 | 1 | $81.25 | -8.7% | 16 |
| 08 | 5 | $107.73 | +21.1% | 391 |
| 09 | 1 | $100.00 | +12.4% | 98 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0705 11 2 (Delineator, NON-Flexible) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 18 contracts with a quantity-weighted average of $88.98 per EA, on 1,503 EA worth $133,741 in total.
The same report run for earlier periods shows $101.74 in 2024 (20 contracts, 841 EA), $109.83 in 2025 (23 contracts, 1,574 EA), $88.98 in the latest 12 months (18 contracts, 1,503 EA). From 2024 to the latest 12 months the weighted average fell 12.5%.
Quantity let statewide grew 79% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 3 market areas with at least three contracts, market area 04 had the lowest weighted average ($63.98 per EA, 3 contracts) and market area 08 the highest ($107.73, 5 contracts), 1.7 times as much. Market area 08 let the most contracts with this item (5). 8 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0705: 0705 10 1 Object Marker, Type 1 ($291.73 per EA, 77 contracts); 0705 11 1 Delineator, Flexible Tubular ($120.50 per EA, 45 contracts); 0705 10 3 Object Marker, Type 3 ($302.51 per EA, 27 contracts); 0705 10 2 Object Marker, Type 2 ($127.47 per EA, 22 contracts); 0705 10 4 Object Marker, Type 4 ($313.29 per EA, 8 contracts).
Related items in section 0705
- 0705 10 1 · Object Marker, Type 1 ($291.73/EA)
- 0705 11 1 · Delineator, Flexible Tubular ($120.50/EA)
- 0705 10 3 · Object Marker, Type 3 ($302.51/EA)
- 0705 10 2 · Object Marker, Type 2 ($127.47/EA)
- 0705 10 4 · Object Marker, Type 4 ($313.29/EA)
- 0705 11 9 · Delineator, Furnish & Install ON Existing Barrier ($172.47/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.