Object Marker, Type 2 (Item 0705 10 2): FDOT Unit Price History
22 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $127.47/EA
- Contracts (12 mo)
- 22
- Total quantity (12 mo)
- 522 EA
- Total amount (12 mo)
- $66,541
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 23 | $147.95 | 1,007 | $148,988 |
| 2025 | 2025-01-01 – 2025-12-31 | 21 | $183.25 | 258 | $47,277 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 22 | $127.47 | 522 | $66,541 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 02 | 1 | $56.07 | -56% | 17 |
| 03 | 1 | $69.05 | -45.8% | 20 |
| 04 | 7 | $99.57 | -21.9% | 193 |
| 05 | 1 | $80.00 | -37.2% | 16 |
| 06 | 2 | $137.03 | +7.5% | 32 |
| 07 | 3 | $120.50 | -5.5% | 113 |
| 08 | 1 | $264.72 | +107.7% | 1 |
| 09 | 1 | $100.00 | -21.6% | 87 |
| 10 | 1 | $120.00 | -5.9% | 2 |
| 11 | 2 | $347.73 | +172.8% | 20 |
| 12 | 1 | $450.00 | +253% | 1 |
| 13 | 1 | $455.00 | +256.9% | 20 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0705 10 2 (Object Marker, Type 2) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 22 contracts with a quantity-weighted average of $127.47 per EA, on 522 EA worth $66,541 in total.
The same report run for earlier periods shows $147.95 in 2024 (23 contracts, 1,007 EA), $183.25 in 2025 (21 contracts, 258 EA), $127.47 in the latest 12 months (22 contracts, 522 EA). From 2024 to the latest 12 months the weighted average fell 13.8%.
Quantity let statewide shrank 48% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 12 of FDOT's 14 market areas reported this item: area 02 at $56.07 (1 contract), area 03 at $69.05 (1 contract), area 04 at $99.57 (7 contracts), area 05 at $80.00 (1 contract), area 06 at $137.03 (2 contracts), area 07 at $120.50 (3 contracts), area 08 at $264.72 (1 contract), area 09 at $100.00 (1 contract), area 10 at $120.00 (1 contract), area 11 at $347.73 (2 contracts), area 12 at $450.00 (1 contract), area 13 at $455.00 (1 contract).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0705: 0705 10 1 Object Marker, Type 1 ($291.73 per EA, 77 contracts); 0705 11 1 Delineator, Flexible Tubular ($120.50 per EA, 45 contracts); 0705 10 3 Object Marker, Type 3 ($302.51 per EA, 27 contracts); 0705 11 2 Delineator, NON-Flexible ($88.98 per EA, 18 contracts); 0705 10 4 Object Marker, Type 4 ($313.29 per EA, 8 contracts).
Related items in section 0705
- 0705 10 1 · Object Marker, Type 1 ($291.73/EA)
- 0705 11 1 · Delineator, Flexible Tubular ($120.50/EA)
- 0705 10 3 · Object Marker, Type 3 ($302.51/EA)
- 0705 11 2 · Delineator, NON-Flexible ($88.98/EA)
- 0705 10 4 · Object Marker, Type 4 ($313.29/EA)
- 0705 11 9 · Delineator, Furnish & Install ON Existing Barrier ($172.47/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.