ITS Cabinet, Furnish & Install, Base Mount, 334, 24" W X 66" H X 30" D (Item 0676 2143): FDOT Unit Price History

14 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA

Weighted average (12 mo)
$13,378.72/EA
Contracts (12 mo)
14
Total quantity (12 mo)
70 EA
Total amount (12 mo)
$936,510

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-3121$13,305.11116$1,543,393
20252025-01-01 – 2025-12-3119$14,340.9975$1,075,575
Latest 12 months2025-11-01 – 2026-10-3114$13,378.7270$936,510

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
051$12,241.00-8.5%12
062$14,120.57+5.5%14
072$14,517.00+8.5%4
084$15,066.75+12.6%18
125$11,939.13-10.8%22

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0676 2143 (ITS Cabinet, Furnish & Install, Base Mount, 334, 24" W X 66" H X 30" D) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 14 contracts with a quantity-weighted average of $13,378.72 per EA, on 70 EA worth $936,510 in total.

The same report run for earlier periods shows $13,305.11 in 2024 (21 contracts, 116 EA), $14,340.99 in 2025 (19 contracts, 75 EA), $13,378.72 in the latest 12 months (14 contracts, 70 EA). Across those periods the weighted average stayed within three percent.

Quantity let statewide shrank 40% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

In the same 12 months, 5 of FDOT's 14 market areas reported this item: area 05 at $12,241.00 (1 contract), area 06 at $14,120.57 (2 contracts), area 07 at $14,517.00 (2 contracts), area 08 at $15,066.75 (4 contracts), area 12 at $11,939.13 (5 contracts).

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0676: 0676 1500 Traffic Signal Controller Cabinet, Adjust/Modify ($2,596.63 per EA, 25 contracts); 0676 2122 ITS Cabinet, Furnish & Install, Pole Mount With Sunshield, 336S, 24" W X 46" H X 22" D ($9,004.69 per EA, 15 contracts); 0676 2500 ITS Cabinet- Adjust/Modify ($2,953.98 per EA, 10 contracts); 0676 3 10 Small Equipment Enclosure, Furnish AND Install, Less Than 10"W X 13"H X 11" D ($2,252.83 per EA, 8 contracts); 0676 1600 Traffic Signal Controller Cabinet, Remove ($1,037.92 per EA, 6 contracts).

Related items in section 0676

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.