Traffic Signal Controller Cabinet, Adjust/Modify (Item 0676 1500): FDOT Unit Price History
25 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $2,596.63/EA
- Contracts (12 mo)
- 25
- Total quantity (12 mo)
- 62 EA
- Total amount (12 mo)
- $160,991
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 41 | $3,653.14 | 101 | $368,967 |
| 2025 | 2025-01-01 – 2025-12-31 | 27 | $3,474.06 | 79 | $274,451 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 25 | $2,596.63 | 62 | $160,991 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 05 | 1 | $900.00 | -65.3% | 3 |
| 06 | 2 | $2,593.65 | -0.1% | 4 |
| 07 | 3 | $2,684.03 | +3.4% | 11 |
| 08 | 8 | $2,692.57 | +3.7% | 23 |
| 09 | 1 | $3,638.11 | +40.1% | 1 |
| 10 | 3 | $4,200.20 | +61.8% | 4 |
| 12 | 7 | $2,251.50 | -13.3% | 16 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0676 1500 (Traffic Signal Controller Cabinet, Adjust/Modify) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 25 contracts with a quantity-weighted average of $2,596.63 per EA, on 62 EA worth $160,991 in total.
The same report run for earlier periods shows $3,653.14 in 2024 (41 contracts, 101 EA), $3,474.06 in 2025 (27 contracts, 79 EA), $2,596.63 in the latest 12 months (25 contracts, 62 EA). From 2024 to the latest 12 months the weighted average fell 28.9%.
Quantity let statewide shrank 39% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 4 market areas with at least three contracts, market area 12 had the lowest weighted average ($2,251.50 per EA, 7 contracts) and market area 10 the highest ($4,200.20, 3 contracts), 1.9 times as much. Market area 08 let the most contracts with this item (8). 7 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0676: 0676 2122 ITS Cabinet, Furnish & Install, Pole Mount With Sunshield, 336S, 24" W X 46" H X 22" D ($9,004.69 per EA, 15 contracts); 0676 2143 ITS Cabinet, Furnish & Install, Base Mount, 334, 24" W X 66" H X 30" D ($13,378.72 per EA, 14 contracts); 0676 2500 ITS Cabinet- Adjust/Modify ($2,953.98 per EA, 10 contracts); 0676 3 10 Small Equipment Enclosure, Furnish AND Install, Less Than 10"W X 13"H X 11" D ($2,252.83 per EA, 8 contracts); 0676 1600 Traffic Signal Controller Cabinet, Remove ($1,037.92 per EA, 6 contracts).
Related items in section 0676
- 0676 2122 · ITS Cabinet, Furnish & Install, Pole Mount With Sunshield, 336S, 24" W X 46" H X 22" D ($9,004.69/EA)
- 0676 2143 · ITS Cabinet, Furnish & Install, Base Mount, 334, 24" W X 66" H X 30" D ($13,378.72/EA)
- 0676 2500 · ITS Cabinet- Adjust/Modify ($2,953.98/EA)
- 0676 3 10 · Small Equipment Enclosure, Furnish AND Install, Less Than 10"W X 13"H X 11" D ($2,252.83/EA)
- 0676 1600 · Traffic Signal Controller Cabinet, Remove ($1,037.92/EA)
- 0676 2600 · ITS Cabinet- Remove ($1,189.14/EA)
- 0676 2400 · ITS Cabinet, Relocate ($3,069.33/EA)
- 0676 1117 · Traffic Signal Controller Cabinet, Furnish & Install Without Controller, Nema SIZE7, 44" W X 72" H X 24" D ($43,894.36/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.