Signal Priority AND Preemption System, F&I, Optical, Detector (Item 0663 1112): FDOT Unit Price History
10 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $3,880.00/EA
- Contracts (12 mo)
- 10
- Total quantity (12 mo)
- 53 EA
- Total amount (12 mo)
- $205,640
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 11 | $3,097.13 | 71 | $219,896 |
| 2025 | 2025-01-01 – 2025-12-31 | 13 | $4,046.84 | 47 | $190,202 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 10 | $3,880.00 | 53 | $205,640 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 1 | $4,500.00 | +16% | 1 |
| 06 | 1 | $3,400.00 | -12.4% | 4 |
| 07 | 1 | $2,197.00 | -43.4% | 4 |
| 08 | 6 | $4,018.80 | +3.6% | 40 |
| 10 | 1 | $4,500.00 | +16% | 4 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0663 1112 (Signal Priority AND Preemption System, F&I, Optical, Detector) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 10 contracts with a quantity-weighted average of $3,880.00 per EA, on 53 EA worth $205,640 in total.
The same report run for earlier periods shows $3,097.13 in 2024 (11 contracts, 71 EA), $4,046.84 in 2025 (13 contracts, 47 EA), $3,880.00 in the latest 12 months (10 contracts, 53 EA). From 2024 to the latest 12 months the weighted average rose 25.3%.
Quantity let statewide shrank 25% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 5 of FDOT's 14 market areas reported this item: area 01 at $4,500.00 (1 contract), area 06 at $3,400.00 (1 contract), area 07 at $2,197.00 (1 contract), area 08 at $4,018.80 (6 contracts), area 10 at $4,500.00 (1 contract).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0663: 0663 1122 Signal Priority AND Preemption System, Furnish AND Install, GPS, Detector ($9,188.67 per EA, 13 contracts); 0663 1123 Signal Priority AND Preemption System, Furnish AND Install, GPS, Cabinet Electronics ($9,218.28 per EA, 12 contracts); 0663 1111 Signal Priority AND Preemption System, F&I, Optical, Cabinet Electronics ($10,215.10 per EA, 8 contracts); 0663 1400 Signal Priority & Preemption System, Relocate ($1,562.14 per EA, 4 contracts); 0663 1500 Signal Priority & Preemption System, Adjust/Modify ($2,113.02 per EA, 3 contracts).
Related items in section 0663
- 0663 1122 · Signal Priority AND Preemption System, Furnish AND Install, GPS, Detector ($9,188.67/EA)
- 0663 1123 · Signal Priority AND Preemption System, Furnish AND Install, GPS, Cabinet Electronics ($9,218.28/EA)
- 0663 1111 · Signal Priority AND Preemption System, F&I, Optical, Cabinet Electronics ($10,215.10/EA)
- 0663 1400 · Signal Priority & Preemption System, Relocate ($1,562.14/EA)
- 0663 1500 · Signal Priority & Preemption System, Adjust/Modify ($2,113.02/EA)
- 0663 1121 · Signal Priority AND Preemption System, Furnish AND Install, GPS, Replace Cabinet Electronics ($9,120.00/EA)
- 0663 1600 · Signal Priority & Preemption System, Remove ($445.00/EA)