Vehicle Detection System- Wrong WAY FOR Exit Ramp, 1 OR 2 Lanes, AC Powered (Item 0660 7 21): FDOT Unit Price History
10 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $46,007.42/EA
- Contracts (12 mo)
- 10
- Total quantity (12 mo)
- 23 EA
- Total amount (12 mo)
- $1,058,171
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 7 | $56,608.13 | 21 | $1,188,771 |
| 2025 | 2025-01-01 – 2025-12-31 | 17 | $60,725.90 | 72 | $4,372,265 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 10 | $46,007.42 | 23 | $1,058,171 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 05 | 2 | $37,331.39 | -18.9% | 7 |
| 06 | 2 | $59,827.50 | +30% | 2 |
| 07 | 2 | $46,375.00 | +0.8% | 4 |
| 08 | 3 | $56,194.79 | +22.1% | 7 |
| 12 | 1 | $32,777.48 | -28.8% | 3 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0660 7 21 (Vehicle Detection System- Wrong WAY FOR Exit Ramp, 1 OR 2 Lanes, AC Powered) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 10 contracts with a quantity-weighted average of $46,007.42 per EA, on 23 EA worth $1,058,171 in total.
The same report run for earlier periods shows $56,608.13 in 2024 (7 contracts, 21 EA), $60,725.90 in 2025 (17 contracts, 72 EA), $46,007.42 in the latest 12 months (10 contracts, 23 EA). From 2024 to the latest 12 months the weighted average fell 18.7%.
In the same 12 months, 5 of FDOT's 14 market areas reported this item: area 05 at $37,331.39 (2 contracts), area 06 at $59,827.50 (2 contracts), area 07 at $46,375.00 (2 contracts), area 08 at $56,194.79 (3 contracts), area 12 at $32,777.48 (1 contract).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0660: 0660 2106 Loop Assembly, F&I, Type F ($1,828.60 per AS, 84 contracts); 0660 2102 Loop Assembly, F&I, Type B ($1,545.86 per AS, 54 contracts); 0660 4 12 Vehicle Detection System- Video, Furnish & Install Above Ground Equipment ($7,890.18 per EA, 43 contracts); 0660 4 11 Vehicle Detection System- Video, Furnish & Install Cabinet Equipment ($14,779.31 per EA, 41 contracts); 0660 1110 Loop Detector Inductive, F&I, Type 10 ($590.20 per EA, 25 contracts).
Related items in section 0660
- 0660 2106 · Loop Assembly, F&I, Type F ($1,828.60/AS)
- 0660 2102 · Loop Assembly, F&I, Type B ($1,545.86/AS)
- 0660 4 12 · Vehicle Detection System- Video, Furnish & Install Above Ground Equipment ($7,890.18/EA)
- 0660 4 11 · Vehicle Detection System- Video, Furnish & Install Cabinet Equipment ($14,779.31/EA)
- 0660 1110 · Loop Detector Inductive, F&I, Type 10 ($590.20/EA)
- 0660 1109 · Loop Detector Inductive, F&I, Type 9 ($477.09/EA)
- 0660 3 11 · Vehicle Detection System- Microwave, Furnish & Install Cabinet Equipment ($11,338.74/EA)
- 0660 3 12 · Vehicle Detection System- Microwave, Furnish & Install, Above Ground Equipment ($12,720.04/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.