Loop Assembly, F&I, Type B (Item 0660 2102): FDOT Unit Price History
54 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure AS
- Weighted average (12 mo)
- $1,545.86/AS
- Contracts (12 mo)
- 54
- Total quantity (12 mo)
- 1,719 AS
- Total amount (12 mo)
- $2,657,334
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 70 | $1,444.19 | 1,495 | $2,159,058 |
| 2025 | 2025-01-01 – 2025-12-31 | 70 | $1,977.48 | 1,622 | $3,207,470 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 54 | $1,545.86 | 1,719 | $2,657,334 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 6 | $1,517.01 | -1.9% | 281 |
| 02 | 4 | $1,595.49 | +3.2% | 18 |
| 03 | 6 | $1,449.56 | -6.2% | 194 |
| 04 | 1 | $1,990.00 | +28.7% | 8 |
| 05 | 6 | $1,986.37 | +28.5% | 148 |
| 06 | 10 | $1,457.25 | -5.7% | 402 |
| 07 | 4 | $1,781.69 | +15.3% | 52 |
| 08 | 8 | $1,534.15 | -0.8% | 385 |
| 09 | 3 | $1,225.57 | -20.7% | 141 |
| 10 | 4 | $1,854.65 | +20% | 86 |
| 12 | 1 | $3,400.00 | +119.9% | 2 |
| 13 | 1 | $1,500.00 | -3% | 2 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0660 2102 (Loop Assembly, F&I, Type B) is measured in AS. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 54 contracts with a quantity-weighted average of $1,545.86 per AS, on 1,719 AS worth $2,657,334 in total.
The same report run for earlier periods shows $1,444.19 in 2024 (70 contracts, 1,495 AS), $1,977.48 in 2025 (70 contracts, 1,622 AS), $1,545.86 in the latest 12 months (54 contracts, 1,719 AS). From 2024 to the latest 12 months the weighted average rose 7.0%.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 9 market areas with at least three contracts, market area 09 had the lowest weighted average ($1,225.57 per AS, 3 contracts) and market area 05 the highest ($1,986.37, 6 contracts), 1.6 times as much. Market area 06 let the most contracts with this item (10). 12 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0660: 0660 2106 Loop Assembly, F&I, Type F ($1,828.60 per AS, 84 contracts); 0660 4 12 Vehicle Detection System- Video, Furnish & Install Above Ground Equipment ($7,890.18 per EA, 43 contracts); 0660 4 11 Vehicle Detection System- Video, Furnish & Install Cabinet Equipment ($14,779.31 per EA, 41 contracts); 0660 1110 Loop Detector Inductive, F&I, Type 10 ($590.20 per EA, 25 contracts); 0660 1109 Loop Detector Inductive, F&I, Type 9 ($477.09 per EA, 24 contracts).
Related items in section 0660
- 0660 2106 · Loop Assembly, F&I, Type F ($1,828.60/AS)
- 0660 4 12 · Vehicle Detection System- Video, Furnish & Install Above Ground Equipment ($7,890.18/EA)
- 0660 4 11 · Vehicle Detection System- Video, Furnish & Install Cabinet Equipment ($14,779.31/EA)
- 0660 1110 · Loop Detector Inductive, F&I, Type 10 ($590.20/EA)
- 0660 1109 · Loop Detector Inductive, F&I, Type 9 ($477.09/EA)
- 0660 3 11 · Vehicle Detection System- Microwave, Furnish & Install Cabinet Equipment ($11,338.74/EA)
- 0660 3 12 · Vehicle Detection System- Microwave, Furnish & Install, Above Ground Equipment ($12,720.04/EA)
- 0660 2101 · Loop Assembly- F&I, Type A ($1,635.50/AS)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.