Loop Detector Inductive, Remove- Cabinet TO Remain (Item 0660 1600): FDOT Unit Price History
11 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $80.14/EA
- Contracts (12 mo)
- 11
- Total quantity (12 mo)
- 366 EA
- Total amount (12 mo)
- $29,331
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 23 | $86.31 | 430 | $37,111 |
| 2025 | 2025-01-01 – 2025-12-31 | 22 | $94.96 | 478 | $45,389 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 11 | $80.14 | 366 | $29,331 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 05 | 2 | $113.99 | +42.2% | 67 |
| 06 | 1 | $53.00 | -33.9% | 131 |
| 07 | 1 | $41.47 | -48.3% | 55 |
| 08 | 2 | $126.28 | +57.6% | 53 |
| 10 | 1 | $81.00 | +1.1% | 5 |
| 13 | 4 | $97.68 | +21.9% | 55 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0660 1600 (Loop Detector Inductive, Remove- Cabinet TO Remain) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 11 contracts with a quantity-weighted average of $80.14 per EA, on 366 EA worth $29,331 in total.
The same report run for earlier periods shows $86.31 in 2024 (23 contracts, 430 EA), $94.96 in 2025 (22 contracts, 478 EA), $80.14 in the latest 12 months (11 contracts, 366 EA). From 2024 to the latest 12 months the weighted average fell 7.1%.
In the same 12 months, 6 of FDOT's 14 market areas reported this item: area 05 at $113.99 (2 contracts), area 06 at $53.00 (1 contract), area 07 at $41.47 (1 contract), area 08 at $126.28 (2 contracts), area 10 at $81.00 (1 contract), area 13 at $97.68 (4 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0660: 0660 2106 Loop Assembly, F&I, Type F ($1,828.60 per AS, 84 contracts); 0660 2102 Loop Assembly, F&I, Type B ($1,545.86 per AS, 54 contracts); 0660 4 12 Vehicle Detection System- Video, Furnish & Install Above Ground Equipment ($7,890.18 per EA, 43 contracts); 0660 4 11 Vehicle Detection System- Video, Furnish & Install Cabinet Equipment ($14,779.31 per EA, 41 contracts); 0660 1110 Loop Detector Inductive, F&I, Type 10 ($590.20 per EA, 25 contracts).
Related items in section 0660
- 0660 2106 · Loop Assembly, F&I, Type F ($1,828.60/AS)
- 0660 2102 · Loop Assembly, F&I, Type B ($1,545.86/AS)
- 0660 4 12 · Vehicle Detection System- Video, Furnish & Install Above Ground Equipment ($7,890.18/EA)
- 0660 4 11 · Vehicle Detection System- Video, Furnish & Install Cabinet Equipment ($14,779.31/EA)
- 0660 1110 · Loop Detector Inductive, F&I, Type 10 ($590.20/EA)
- 0660 1109 · Loop Detector Inductive, F&I, Type 9 ($477.09/EA)
- 0660 3 11 · Vehicle Detection System- Microwave, Furnish & Install Cabinet Equipment ($11,338.74/EA)
- 0660 3 12 · Vehicle Detection System- Microwave, Furnish & Install, Above Ground Equipment ($12,720.04/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.