Riprap- Rubble, Bank AND Shore (Item 0530 3 3): FDOT Unit Price History
24 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure TN
- Weighted average (12 mo)
- $181.89/TN
- Contracts (12 mo)
- 24
- Total quantity (12 mo)
- 28,555.1 TN
- Total amount (12 mo)
- $5,193,829
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 21 | $105.95 | 195,524.5 | $20,716,645 |
| 2025 | 2025-01-01 – 2025-12-31 | 19 | $143.61 | 42,668.8 | $6,127,728 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 24 | $181.89 | 28,555.1 | $5,193,829 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 6 | $286.51 | +57.5% | 7,193.4 |
| 02 | 6 | $126.02 | -30.7% | 5,130.7 |
| 03 | 2 | $130.61 | -28.2% | 4,956.7 |
| 04 | 3 | $170.27 | -6.4% | 4,219.1 |
| 05 | 1 | $187.98 | +3.3% | 1,273 |
| 07 | 1 | $157.00 | -13.7% | 1,688.4 |
| 08 | 1 | $1,600.00 | +779.7% | 25.5 |
| 10 | 1 | $190.00 | +4.5% | 1,360.1 |
| 11 | 1 | $103.30 | -43.2% | 2,176.7 |
| 13 | 2 | $173.11 | -4.8% | 531.5 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0530 3 3 (Riprap- Rubble, Bank AND Shore) is measured in TN. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 24 contracts with a quantity-weighted average of $181.89 per TN, on 28,555.1 TN worth $5,193,829 in total.
The same report run for earlier periods shows $105.95 in 2024 (21 contracts, 195,524.5 TN), $143.61 in 2025 (19 contracts, 42,668.8 TN), $181.89 in the latest 12 months (24 contracts, 28,555.1 TN). From 2024 to the latest 12 months the weighted average rose 71.7%.
Quantity let statewide shrank 85% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 3 market areas with at least three contracts, market area 02 had the lowest weighted average ($126.02 per TN, 6 contracts) and market area 01 the highest ($286.51, 6 contracts), 2.3 times as much. Market area 01 let the most contracts with this item (6). 10 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0530: 0530 74 Bedding Stone ($127.87 per TN, 52 contracts); 0530 3 4 Riprap, Rubble, F&I, Ditch Lining ($126.76 per TN, 46 contracts); 0530 1100 Riprap, Sand-Cement Bags ($1,203.13 per CY, 20 contracts); 0530 4 6 Articulating Concrete Block Revetment System, Thickness 6" ($229.05 per SY, 3 contracts); 0530 3 5 Riprap- Rubble, Coastal Shore- Large Boulders ($150.09 per TN, 2 contracts).
Related items in section 0530
- 0530 74 · Bedding Stone ($127.87/TN)
- 0530 3 4 · Riprap, Rubble, F&I, Ditch Lining ($126.76/TN)
- 0530 1100 · Riprap, Sand-Cement Bags ($1,203.13/CY)
- 0530 4 6 · Articulating Concrete Block Revetment System, Thickness 6" ($229.05/SY)
- 0530 3 5 · Riprap- Rubble, Coastal Shore- Large Boulders ($150.09/TN)
- 0530 4 4 · Articulating Concrete Block Revetment System, Thickness 4" ($277.91/SY)
- 0530 5 12 · Gabion, Mattress 1 Foot AND Greater Thickness ($249.50/SY)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.