Concrete Slope Pavement,NON Reinforced, 4" (Item 0524 2 2): FDOT Unit Price History

17 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure SY

Weighted average (12 mo)
$130.31/SY
Contracts (12 mo)
17
Total quantity (12 mo)
12,716 SY
Total amount (12 mo)
$1,657,063

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-3111$147.696,159$909,628
20252025-01-01 – 2025-12-3121$159.9620,166$3,225,833
Latest 12 months2025-11-01 – 2026-10-3117$130.3112,716$1,657,063

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
032$210.93+61.9%123
041$140.00+7.4%732
052$76.17-41.5%54
061$225.00+72.7%233
073$146.76+12.6%6,569
082$90.06-30.9%3,708
101$240.00+84.2%49
125$130.10-0.2%1,248

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0524 2 2 (Concrete Slope Pavement,NON Reinforced, 4") is measured in SY. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 17 contracts with a quantity-weighted average of $130.31 per SY, on 12,716 SY worth $1,657,063 in total.

The same report run for earlier periods shows $147.69 in 2024 (11 contracts, 6,159 SY), $159.96 in 2025 (21 contracts, 20,166 SY), $130.31 in the latest 12 months (17 contracts, 12,716 SY). From 2024 to the latest 12 months the weighted average fell 11.8%.

Quantity let statewide grew 106% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

In the same 12 months, 8 of FDOT's 14 market areas reported this item: area 03 at $210.93 (2 contracts), area 04 at $140.00 (1 contract), area 05 at $76.17 (2 contracts), area 06 at $225.00 (1 contract), area 07 at $146.76 (3 contracts), area 08 at $90.06 (2 contracts), area 10 at $240.00 (1 contract), area 12 at $130.10 (5 contracts).

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0524: 0524 1 2 Concrete Ditch Pavement, NON Reinforced, 4" ($84.77 per SY, 26 contracts); 0524 1 1 Concrete Ditch Pavt, NON Reinforced, 3" ($76.61 per SY, 17 contracts); 0524 1 29 Concrete Ditch Pavement, 4", Reinforced ($150.33 per SY, 10 contracts); 0524 1 4 Concrete Ditch Pavement, NON Reinforced, 6" ($145.08 per SY, 10 contracts); 0524 1 49 Concrete Ditch Pavement, 6", Reinforced ($138.44 per SY, 5 contracts).

Related items in section 0524

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.