Concrete Ditch Pavement, 4", Reinforced (Item 0524 1 29): FDOT Unit Price History
10 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure SY
- Weighted average (12 mo)
- $150.33/SY
- Contracts (12 mo)
- 10
- Total quantity (12 mo)
- 908 SY
- Total amount (12 mo)
- $136,497
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 17 | $127.91 | 3,741 | $478,524 |
| 2025 | 2025-01-01 – 2025-12-31 | 18 | $171.14 | 8,701 | $1,489,108 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 10 | $150.33 | 908 | $136,497 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 1 | $156.92 | +4.4% | 79 |
| 03 | 1 | $563.57 | +274.9% | 11 |
| 04 | 1 | $124.72 | -17% | 420 |
| 06 | 1 | $173.00 | +15.1% | 228 |
| 08 | 3 | $140.15 | -6.8% | 81 |
| 09 | 2 | $200.84 | +33.6% | 50 |
| 13 | 1 | $120.00 | -20.2% | 39 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0524 1 29 (Concrete Ditch Pavement, 4", Reinforced) is measured in SY. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 10 contracts with a quantity-weighted average of $150.33 per SY, on 908 SY worth $136,497 in total.
The same report run for earlier periods shows $127.91 in 2024 (17 contracts, 3,741 SY), $171.14 in 2025 (18 contracts, 8,701 SY), $150.33 in the latest 12 months (10 contracts, 908 SY). From 2024 to the latest 12 months the weighted average rose 17.5%.
Quantity let statewide shrank 76% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 7 of FDOT's 14 market areas reported this item: area 01 at $156.92 (1 contract), area 03 at $563.57 (1 contract), area 04 at $124.72 (1 contract), area 06 at $173.00 (1 contract), area 08 at $140.15 (3 contracts), area 09 at $200.84 (2 contracts), area 13 at $120.00 (1 contract).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0524: 0524 1 2 Concrete Ditch Pavement, NON Reinforced, 4" ($84.77 per SY, 26 contracts); 0524 1 1 Concrete Ditch Pavt, NON Reinforced, 3" ($76.61 per SY, 17 contracts); 0524 2 2 Concrete Slope Pavement,NON Reinforced, 4" ($130.31 per SY, 17 contracts); 0524 1 4 Concrete Ditch Pavement, NON Reinforced, 6" ($145.08 per SY, 10 contracts); 0524 1 49 Concrete Ditch Pavement, 6", Reinforced ($138.44 per SY, 5 contracts).
Related items in section 0524
- 0524 1 2 · Concrete Ditch Pavement, NON Reinforced, 4" ($84.77/SY)
- 0524 1 1 · Concrete Ditch Pavt, NON Reinforced, 3" ($76.61/SY)
- 0524 2 2 · Concrete Slope Pavement,NON Reinforced, 4" ($130.31/SY)
- 0524 1 4 · Concrete Ditch Pavement, NON Reinforced, 6" ($145.08/SY)
- 0524 1 49 · Concrete Ditch Pavement, 6", Reinforced ($138.44/SY)
- 0524 2 1 · Concrete Slope Pavement,NON Reinforced, 3" ($154.14/SY)
- 0524 2 49 · Concrete Slope Pavement, 6", Reinforced ($222.45/SY)
- 0524 3 · Conc Core Ditch Blocks ($1,078.27/CY)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.