Pedestrian/ Bicycle Railing, Aluminum Only,42" Type 1 (Item 0515 2311): FDOT Unit Price History
10 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF
- Weighted average (12 mo)
- $111.04/LF
- Contracts (12 mo)
- 10
- Total quantity (12 mo)
- 7,961 LF
- Total amount (12 mo)
- $884,001
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 12 | $90.34 | 5,285 | $477,472 |
| 2025 | 2025-01-01 – 2025-12-31 | 17 | $124.34 | 11,267 | $1,400,964 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 10 | $111.04 | 7,961 | $884,001 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 03 | 1 | $84.00 | -24.4% | 117 |
| 05 | 2 | $144.67 | +30.3% | 598 |
| 06 | 1 | $90.00 | -18.9% | 44 |
| 08 | 4 | $119.38 | +7.5% | 4,728 |
| 11 | 1 | $87.00 | -21.6% | 1,806 |
| 13 | 1 | $93.00 | -16.2% | 668 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0515 2311 (Pedestrian/ Bicycle Railing, Aluminum Only,42" Type 1) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 10 contracts with a quantity-weighted average of $111.04 per LF, on 7,961 LF worth $884,001 in total.
The same report run for earlier periods shows $90.34 in 2024 (12 contracts, 5,285 LF), $124.34 in 2025 (17 contracts, 11,267 LF), $111.04 in the latest 12 months (10 contracts, 7,961 LF). From 2024 to the latest 12 months the weighted average rose 22.9%.
Quantity let statewide grew 51% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 6 of FDOT's 14 market areas reported this item: area 03 at $84.00 (1 contract), area 05 at $144.67 (2 contracts), area 06 at $90.00 (1 contract), area 08 at $119.38 (4 contracts), area 11 at $87.00 (1 contract), area 13 at $93.00 (1 contract).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0515: 0515 1 2 Pipe Handrail - Guiderail, Aluminum ($77.10 per LF, 32 contracts); 0515 1 1 Pipe Handrail - Guiderail, Steel ($102.12 per LF, 13 contracts); 0515 4 2 Bullet Rail, Double Rail ($63.67 per LF, 6 contracts); 0515 2111 Pedestrian / Bicycle Railing, NS, 42" Type 1 ($144.31 per LF, 5 contracts); 0515 2211 Pedestrian / Bicycle Railing, Steel, 42" Type 1 ($105.03 per LF, 5 contracts).
Related items in section 0515
- 0515 1 2 · Pipe Handrail - Guiderail, Aluminum ($77.10/LF)
- 0515 1 1 · Pipe Handrail - Guiderail, Steel ($102.12/LF)
- 0515 4 2 · Bullet Rail, Double Rail ($63.67/LF)
- 0515 2111 · Pedestrian / Bicycle Railing, NS, 42" Type 1 ($144.31/LF)
- 0515 2211 · Pedestrian / Bicycle Railing, Steel, 42" Type 1 ($105.03/LF)
- 0515 1 42 · Pipe Handrail - Guiderail, Relocate, Aluminum ($106.93/LF)
- 0515 4 1 · Bullet Rail, Single Rail ($109.10/LF)
- 0515 2231 · Pedestrian/ Bicycle Railing, Steel Only,48" Type 1 ($127.50/LF)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.