Pipe Handrail - Guiderail, Steel (Item 0515 1 1): FDOT Unit Price History

13 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF

Weighted average (12 mo)
$102.12/LF
Contracts (12 mo)
13
Total quantity (12 mo)
5,398 LF
Total amount (12 mo)
$551,229

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-3111$160.84381$61,279
20252025-01-01 – 2025-12-319$104.711,941$203,234
Latest 12 months2025-11-01 – 2026-10-3113$102.125,398$551,229

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
073$94.93-7%3,302
083$78.89-22.7%1,410
091$70.00-31.5%18
101$84.89-16.9%102
112$210.98+106.6%65
122$91.88-10%117
131$240.00+135%384

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0515 1 1 (Pipe Handrail - Guiderail, Steel) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 13 contracts with a quantity-weighted average of $102.12 per LF, on 5,398 LF worth $551,229 in total.

The same report run for earlier periods shows $160.84 in 2024 (11 contracts, 381 LF), $104.71 in 2025 (9 contracts, 1,941 LF), $102.12 in the latest 12 months (13 contracts, 5,398 LF). From 2024 to the latest 12 months the weighted average fell 36.5%.

Quantity let statewide grew 1317% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

In the same 12 months, 7 of FDOT's 14 market areas reported this item: area 07 at $94.93 (3 contracts), area 08 at $78.89 (3 contracts), area 09 at $70.00 (1 contract), area 10 at $84.89 (1 contract), area 11 at $210.98 (2 contracts), area 12 at $91.88 (2 contracts), area 13 at $240.00 (1 contract).

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0515: 0515 1 2 Pipe Handrail - Guiderail, Aluminum ($77.10 per LF, 32 contracts); 0515 2311 Pedestrian/ Bicycle Railing, Aluminum Only,42" Type 1 ($111.04 per LF, 10 contracts); 0515 4 2 Bullet Rail, Double Rail ($63.67 per LF, 6 contracts); 0515 2111 Pedestrian / Bicycle Railing, NS, 42" Type 1 ($144.31 per LF, 5 contracts); 0515 2211 Pedestrian / Bicycle Railing, Steel, 42" Type 1 ($105.03 per LF, 5 contracts).

Related items in section 0515

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.