Manholes, J-8, >10' (Item 0425 2 92): FDOT Unit Price History
12 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $18,945.30/EA
- Contracts (12 mo)
- 12
- Total quantity (12 mo)
- 32 EA
- Total amount (12 mo)
- $606,250
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 13 | $19,162.88 | 101 | $1,935,451 |
| 2025 | 2025-01-01 – 2025-12-31 | 14 | $18,730.20 | 71 | $1,329,844 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 12 | $18,945.30 | 32 | $606,250 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 1 | $11,700.00 | -38.2% | 4 |
| 03 | 1 | $14,048.86 | -25.8% | 2 |
| 06 | 1 | $25,121.00 | +32.6% | 3 |
| 07 | 3 | $17,671.43 | -6.7% | 14 |
| 08 | 2 | $17,683.50 | -6.7% | 4 |
| 10 | 2 | $14,162.50 | -25.2% | 2 |
| 12 | 2 | $36,510.00 | +92.7% | 3 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0425 2 92 (Manholes, J-8, >10') is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 12 contracts with a quantity-weighted average of $18,945.30 per EA, on 32 EA worth $606,250 in total.
The same report run for earlier periods shows $19,162.88 in 2024 (13 contracts, 101 EA), $18,730.20 in 2025 (14 contracts, 71 EA), $18,945.30 in the latest 12 months (12 contracts, 32 EA). Across those periods the weighted average stayed within three percent.
Quantity let statewide shrank 68% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 7 of FDOT's 14 market areas reported this item: area 01 at $11,700.00 (1 contract), area 03 at $14,048.86 (1 contract), area 06 at $25,121.00 (1 contract), area 07 at $17,671.43 (3 contracts), area 08 at $17,683.50 (2 contracts), area 10 at $14,162.50 (2 contracts), area 12 at $36,510.00 (2 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0425: 0425 5 Manhole, Adjust ($1,119.50 per EA, 80 contracts); 0425 6 Valve Boxes, Adjust ($983.70 per EA, 53 contracts); 0425 5 1 Manhole, Adjust, Utilities ($1,452.45 per EA, 41 contracts); 0425 1351 Inlets, Curb, Type P-5, <10' ($9,463.26 per EA, 38 contracts); 0425 1521 Inlets, DT BOT, Type C,<10' ($6,260.63 per EA, 38 contracts).
Related items in section 0425
- 0425 5 · Manhole, Adjust ($1,119.50/EA)
- 0425 6 · Valve Boxes, Adjust ($983.70/EA)
- 0425 5 1 · Manhole, Adjust, Utilities ($1,452.45/EA)
- 0425 1351 · Inlets, Curb, Type P-5, <10' ($9,463.26/EA)
- 0425 1521 · Inlets, DT BOT, Type C,<10' ($6,260.63/EA)
- 0425 1541 · Inlets, DT BOT, Type D, <10' ($7,311.31/EA)
- 0425 2 61 · Manholes, P-8, <10' ($7,273.90/EA)
- 0425 2 41 · Manholes, P-7, <10' ($7,512.23/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.