Valve Boxes, Adjust (Item 0425 6): FDOT Unit Price History
53 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $983.70/EA
- Contracts (12 mo)
- 53
- Total quantity (12 mo)
- 774 EA
- Total amount (12 mo)
- $761,387
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 84 | $940.44 | 2,051 | $1,928,834 |
| 2025 | 2025-01-01 – 2025-12-31 | 67 | $957.89 | 1,007 | $964,590 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 53 | $983.70 | 774 | $761,387 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 5 | $773.37 | -21.4% | 82 |
| 02 | 3 | $2,126.86 | +116.2% | 29 |
| 03 | 6 | $921.08 | -6.4% | 176 |
| 04 | 4 | $850.43 | -13.5% | 47 |
| 05 | 12 | $1,383.04 | +40.6% | 143 |
| 06 | 3 | $833.10 | -15.3% | 29 |
| 07 | 3 | $519.57 | -47.2% | 32 |
| 08 | 5 | $572.90 | -41.8% | 71 |
| 10 | 1 | $2,100.00 | +113.5% | 4 |
| 11 | 1 | $1,100.00 | +11.8% | 12 |
| 12 | 9 | $895.07 | -9% | 147 |
| 13 | 1 | $900.00 | -8.5% | 2 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0425 6 (Valve Boxes, Adjust) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 53 contracts with a quantity-weighted average of $983.70 per EA, on 774 EA worth $761,387 in total.
The same report run for earlier periods shows $940.44 in 2024 (84 contracts, 2,051 EA), $957.89 in 2025 (67 contracts, 1,007 EA), $983.70 in the latest 12 months (53 contracts, 774 EA). From 2024 to the latest 12 months the weighted average rose 4.6%.
Quantity let statewide shrank 62% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 9 market areas with at least three contracts, market area 07 had the lowest weighted average ($519.57 per EA, 3 contracts) and market area 02 the highest ($2,126.86, 3 contracts), 4.1 times as much. Market area 05 let the most contracts with this item (12). 12 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0425: 0425 5 Manhole, Adjust ($1,119.50 per EA, 80 contracts); 0425 5 1 Manhole, Adjust, Utilities ($1,452.45 per EA, 41 contracts); 0425 1351 Inlets, Curb, Type P-5, <10' ($9,463.26 per EA, 38 contracts); 0425 1521 Inlets, DT BOT, Type C,<10' ($6,260.63 per EA, 38 contracts); 0425 1541 Inlets, DT BOT, Type D, <10' ($7,311.31 per EA, 35 contracts).
Related items in section 0425
- 0425 5 · Manhole, Adjust ($1,119.50/EA)
- 0425 5 1 · Manhole, Adjust, Utilities ($1,452.45/EA)
- 0425 1351 · Inlets, Curb, Type P-5, <10' ($9,463.26/EA)
- 0425 1521 · Inlets, DT BOT, Type C,<10' ($6,260.63/EA)
- 0425 1541 · Inlets, DT BOT, Type D, <10' ($7,311.31/EA)
- 0425 2 61 · Manholes, P-8, <10' ($7,273.90/EA)
- 0425 2 41 · Manholes, P-7, <10' ($7,512.23/EA)
- 0425 2 71 · Manholes, J-7, <10' ($13,111.90/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.