Manholes, J-8, <10' (Item 0425 2 91): FDOT Unit Price History
26 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $11,381.18/EA
- Contracts (12 mo)
- 26
- Total quantity (12 mo)
- 122 EA
- Total amount (12 mo)
- $1,388,504
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 29 | $15,007.32 | 105 | $1,575,769 |
| 2025 | 2025-01-01 – 2025-12-31 | 22 | $13,146.89 | 81 | $1,064,898 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 26 | $11,381.18 | 122 | $1,388,504 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 1 | $8,100.00 | -28.8% | 10 |
| 03 | 1 | $10,172.18 | -10.6% | 6 |
| 05 | 2 | $10,637.50 | -6.5% | 2 |
| 06 | 1 | $14,610.00 | +28.4% | 3 |
| 07 | 4 | $9,086.84 | -20.2% | 38 |
| 08 | 9 | $13,452.66 | +18.2% | 45 |
| 10 | 2 | $17,101.21 | +50.3% | 4 |
| 11 | 1 | $12,500.00 | +9.8% | 1 |
| 12 | 5 | $11,522.42 | +1.2% | 13 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0425 2 91 (Manholes, J-8, <10') is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 26 contracts with a quantity-weighted average of $11,381.18 per EA, on 122 EA worth $1,388,504 in total.
The same report run for earlier periods shows $15,007.32 in 2024 (29 contracts, 105 EA), $13,146.89 in 2025 (22 contracts, 81 EA), $11,381.18 in the latest 12 months (26 contracts, 122 EA). From 2024 to the latest 12 months the weighted average fell 24.2%.
Quantity let statewide grew 16% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 3 market areas with at least three contracts, market area 07 had the lowest weighted average ($9,086.84 per EA, 4 contracts) and market area 08 the highest ($13,452.66, 9 contracts), 1.5 times as much. Market area 08 let the most contracts with this item (9). 9 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0425: 0425 5 Manhole, Adjust ($1,119.50 per EA, 80 contracts); 0425 6 Valve Boxes, Adjust ($983.70 per EA, 53 contracts); 0425 5 1 Manhole, Adjust, Utilities ($1,452.45 per EA, 41 contracts); 0425 1351 Inlets, Curb, Type P-5, <10' ($9,463.26 per EA, 38 contracts); 0425 1521 Inlets, DT BOT, Type C,<10' ($6,260.63 per EA, 38 contracts).
Related items in section 0425
- 0425 5 · Manhole, Adjust ($1,119.50/EA)
- 0425 6 · Valve Boxes, Adjust ($983.70/EA)
- 0425 5 1 · Manhole, Adjust, Utilities ($1,452.45/EA)
- 0425 1351 · Inlets, Curb, Type P-5, <10' ($9,463.26/EA)
- 0425 1521 · Inlets, DT BOT, Type C,<10' ($6,260.63/EA)
- 0425 1541 · Inlets, DT BOT, Type D, <10' ($7,311.31/EA)
- 0425 2 61 · Manholes, P-8, <10' ($7,273.90/EA)
- 0425 2 41 · Manholes, P-7, <10' ($7,512.23/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.