Skip to content
BidTabulation.comDOT bid tabulations & unit-price intelligence
Menu

Manholes, P-8, Partial (Item 0425 2 63): FDOT Unit Price History

22 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA

Weighted average (12 mo)
$7,060.62/EA
Contracts (12 mo)
22
Total quantity (12 mo)
56 EA
Total amount (12 mo)
$395,395

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-3119$5,632.0044$247,808
20252025-01-01 – 2025-12-3113$6,064.8650$303,243
Latest 12 months2025-11-01 – 2026-10-3122$7,060.6256$395,395

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
021$7,500.00+6.2%1
032$3,755.40-46.8%4
052$5,348.00-24.3%10
063$7,983.40+13.1%10
087$8,266.48+17.1%21
102$6,131.56-13.2%2
125$6,712.50-4.9%8

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0425 2 63 (Manholes, P-8, Partial) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 22 contracts with a quantity-weighted average of $7,060.62 per EA, on 56 EA worth $395,395 in total.

The same report run for earlier periods shows $5,632.00 in 2024 (19 contracts, 44 EA), $6,064.86 in 2025 (13 contracts, 50 EA), $7,060.62 in the latest 12 months (22 contracts, 56 EA). From 2024 to the latest 12 months the weighted average rose 25.4%.

Quantity let statewide grew 27% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

FDOT's market-area reports for the same 12 months show how location moves the price. Among the 3 market areas with at least three contracts, market area 12 had the lowest weighted average ($6,712.50 per EA, 5 contracts) and market area 08 the highest ($8,266.48, 7 contracts), 1.2 times as much. Market area 08 let the most contracts with this item (7). 7 of FDOT's 14 market areas reported the item in this window.

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0425: 0425 5 Manhole, Adjust ($1,119.50 per EA, 80 contracts); 0425 6 Valve Boxes, Adjust ($983.70 per EA, 53 contracts); 0425 5 1 Manhole, Adjust, Utilities ($1,452.45 per EA, 41 contracts); 0425 1351 Inlets, Curb, Type P-5, <10' ($9,463.26 per EA, 38 contracts); 0425 1521 Inlets, DT BOT, Type C,<10' ($6,260.63 per EA, 38 contracts).

Related items in section 0425

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.