Inlets, Adjacent Barrier, <=10' (Item 0425 1921): FDOT Unit Price History
12 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $8,613.35/EA
- Contracts (12 mo)
- 12
- Total quantity (12 mo)
- 200 EA
- Total amount (12 mo)
- $1,722,671
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 14 | $9,336.64 | 224 | $2,091,407 |
| 2025 | 2025-01-01 – 2025-12-31 | 19 | $10,044.05 | 443 | $4,449,513 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 12 | $8,613.35 | 200 | $1,722,671 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 03 | 2 | $8,721.29 | +1.3% | 11 |
| 07 | 2 | $10,050.00 | +16.7% | 6 |
| 08 | 1 | $8,241.83 | -4.3% | 2 |
| 11 | 1 | $10,050.00 | +16.7% | 8 |
| 12 | 6 | $8,494.52 | -1.4% | 173 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0425 1921 (Inlets, Adjacent Barrier, <=10') is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 12 contracts with a quantity-weighted average of $8,613.35 per EA, on 200 EA worth $1,722,671 in total.
The same report run for earlier periods shows $9,336.64 in 2024 (14 contracts, 224 EA), $10,044.05 in 2025 (19 contracts, 443 EA), $8,613.35 in the latest 12 months (12 contracts, 200 EA). From 2024 to the latest 12 months the weighted average fell 7.7%.
In the same 12 months, 5 of FDOT's 14 market areas reported this item: area 03 at $8,721.29 (2 contracts), area 07 at $10,050.00 (2 contracts), area 08 at $8,241.83 (1 contract), area 11 at $10,050.00 (1 contract), area 12 at $8,494.52 (6 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0425: 0425 5 Manhole, Adjust ($1,119.50 per EA, 80 contracts); 0425 6 Valve Boxes, Adjust ($983.70 per EA, 53 contracts); 0425 5 1 Manhole, Adjust, Utilities ($1,452.45 per EA, 41 contracts); 0425 1351 Inlets, Curb, Type P-5, <10' ($9,463.26 per EA, 38 contracts); 0425 1521 Inlets, DT BOT, Type C,<10' ($6,260.63 per EA, 38 contracts).
Related items in section 0425
- 0425 5 · Manhole, Adjust ($1,119.50/EA)
- 0425 6 · Valve Boxes, Adjust ($983.70/EA)
- 0425 5 1 · Manhole, Adjust, Utilities ($1,452.45/EA)
- 0425 1351 · Inlets, Curb, Type P-5, <10' ($9,463.26/EA)
- 0425 1521 · Inlets, DT BOT, Type C,<10' ($6,260.63/EA)
- 0425 1541 · Inlets, DT BOT, Type D, <10' ($7,311.31/EA)
- 0425 2 61 · Manholes, P-8, <10' ($7,273.90/EA)
- 0425 2 41 · Manholes, P-7, <10' ($7,512.23/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.