Inlets, Closed Flume (Item 0425 1910): FDOT Unit Price History
13 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $6,320.74/EA
- Contracts (12 mo)
- 13
- Total quantity (12 mo)
- 52 EA
- Total amount (12 mo)
- $328,679
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 29 | $9,368.90 | 171 | $1,602,081 |
| 2025 | 2025-01-01 – 2025-12-31 | 26 | $8,036.36 | 133 | $1,068,836 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 13 | $6,320.74 | 52 | $328,679 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 2 | $4,781.67 | -24.3% | 9 |
| 05 | 2 | $7,040.00 | +11.4% | 5 |
| 06 | 1 | $8,500.00 | +34.5% | 1 |
| 07 | 1 | $4,153.00 | -34.3% | 13 |
| 08 | 3 | $5,785.33 | -8.5% | 10 |
| 09 | 1 | $7,862.61 | +24.4% | 2 |
| 12 | 3 | $9,531.35 | +50.8% | 12 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0425 1910 (Inlets, Closed Flume) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 13 contracts with a quantity-weighted average of $6,320.74 per EA, on 52 EA worth $328,679 in total.
The same report run for earlier periods shows $9,368.90 in 2024 (29 contracts, 171 EA), $8,036.36 in 2025 (26 contracts, 133 EA), $6,320.74 in the latest 12 months (13 contracts, 52 EA). From 2024 to the latest 12 months the weighted average fell 32.5%.
Quantity let statewide shrank 70% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 7 of FDOT's 14 market areas reported this item: area 01 at $4,781.67 (2 contracts), area 05 at $7,040.00 (2 contracts), area 06 at $8,500.00 (1 contract), area 07 at $4,153.00 (1 contract), area 08 at $5,785.33 (3 contracts), area 09 at $7,862.61 (1 contract), area 12 at $9,531.35 (3 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0425: 0425 5 Manhole, Adjust ($1,119.50 per EA, 80 contracts); 0425 6 Valve Boxes, Adjust ($983.70 per EA, 53 contracts); 0425 5 1 Manhole, Adjust, Utilities ($1,452.45 per EA, 41 contracts); 0425 1351 Inlets, Curb, Type P-5, <10' ($9,463.26 per EA, 38 contracts); 0425 1521 Inlets, DT BOT, Type C,<10' ($6,260.63 per EA, 38 contracts).
Related items in section 0425
- 0425 5 · Manhole, Adjust ($1,119.50/EA)
- 0425 6 · Valve Boxes, Adjust ($983.70/EA)
- 0425 5 1 · Manhole, Adjust, Utilities ($1,452.45/EA)
- 0425 1351 · Inlets, Curb, Type P-5, <10' ($9,463.26/EA)
- 0425 1521 · Inlets, DT BOT, Type C,<10' ($6,260.63/EA)
- 0425 1541 · Inlets, DT BOT, Type D, <10' ($7,311.31/EA)
- 0425 2 61 · Manholes, P-8, <10' ($7,273.90/EA)
- 0425 2 41 · Manholes, P-7, <10' ($7,512.23/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.