Inlets, Curb, Type 7, <10' (Item 0425 1471): FDOT Unit Price History
11 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $10,728.31/EA
- Contracts (12 mo)
- 11
- Total quantity (12 mo)
- 37 EA
- Total amount (12 mo)
- $396,948
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 5 | $15,191.02 | 20 | $303,820 |
| 2025 | 2025-01-01 – 2025-12-31 | 8 | $8,751.15 | 22 | $192,525 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 11 | $10,728.31 | 37 | $396,948 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 1 | $8,100.00 | -24.5% | 10 |
| 03 | 2 | $9,972.24 | -7% | 4 |
| 07 | 1 | $16,700.00 | +55.7% | 6 |
| 08 | 4 | $10,636.86 | -0.9% | 13 |
| 10 | 1 | $9,739.98 | -9.2% | 2 |
| 12 | 2 | $9,049.67 | -15.6% | 2 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0425 1471 (Inlets, Curb, Type 7, <10') is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 11 contracts with a quantity-weighted average of $10,728.31 per EA, on 37 EA worth $396,948 in total.
The same report run for earlier periods shows $15,191.02 in 2024 (5 contracts, 20 EA), $8,751.15 in 2025 (8 contracts, 22 EA), $10,728.31 in the latest 12 months (11 contracts, 37 EA). From 2024 to the latest 12 months the weighted average fell 29.4%.
Quantity let statewide grew 85% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 6 of FDOT's 14 market areas reported this item: area 01 at $8,100.00 (1 contract), area 03 at $9,972.24 (2 contracts), area 07 at $16,700.00 (1 contract), area 08 at $10,636.86 (4 contracts), area 10 at $9,739.98 (1 contract), area 12 at $9,049.67 (2 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0425: 0425 5 Manhole, Adjust ($1,119.50 per EA, 80 contracts); 0425 6 Valve Boxes, Adjust ($983.70 per EA, 53 contracts); 0425 5 1 Manhole, Adjust, Utilities ($1,452.45 per EA, 41 contracts); 0425 1351 Inlets, Curb, Type P-5, <10' ($9,463.26 per EA, 38 contracts); 0425 1521 Inlets, DT BOT, Type C,<10' ($6,260.63 per EA, 38 contracts).
Related items in section 0425
- 0425 5 · Manhole, Adjust ($1,119.50/EA)
- 0425 6 · Valve Boxes, Adjust ($983.70/EA)
- 0425 5 1 · Manhole, Adjust, Utilities ($1,452.45/EA)
- 0425 1351 · Inlets, Curb, Type P-5, <10' ($9,463.26/EA)
- 0425 1521 · Inlets, DT BOT, Type C,<10' ($6,260.63/EA)
- 0425 1541 · Inlets, DT BOT, Type D, <10' ($7,311.31/EA)
- 0425 2 61 · Manholes, P-8, <10' ($7,273.90/EA)
- 0425 2 41 · Manholes, P-7, <10' ($7,512.23/EA)