Inlets, Curb Type J-1, <10' (Item 0425 1411): FDOT Unit Price History
12 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $14,684.57/EA
- Contracts (12 mo)
- 12
- Total quantity (12 mo)
- 74 EA
- Total amount (12 mo)
- $1,086,658
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 7 | $21,450.49 | 18 | $386,109 |
| 2025 | 2025-01-01 – 2025-12-31 | 7 | $12,839.09 | 18 | $231,104 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 12 | $14,684.57 | 74 | $1,086,658 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 1 | $10,308.00 | -29.8% | 3 |
| 03 | 1 | $10,913.75 | -25.7% | 9 |
| 05 | 2 | $17,556.25 | +19.6% | 4 |
| 07 | 2 | $13,157.14 | -10.4% | 28 |
| 08 | 4 | $17,429.35 | +18.7% | 28 |
| 10 | 1 | $14,865.00 | +1.2% | 1 |
| 12 | 1 | $15,998.80 | +8.9% | 1 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0425 1411 (Inlets, Curb Type J-1, <10') is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 12 contracts with a quantity-weighted average of $14,684.57 per EA, on 74 EA worth $1,086,658 in total.
The same report run for earlier periods shows $21,450.49 in 2024 (7 contracts, 18 EA), $12,839.09 in 2025 (7 contracts, 18 EA), $14,684.57 in the latest 12 months (12 contracts, 74 EA). From 2024 to the latest 12 months the weighted average fell 31.5%.
Quantity let statewide grew 311% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 7 of FDOT's 14 market areas reported this item: area 01 at $10,308.00 (1 contract), area 03 at $10,913.75 (1 contract), area 05 at $17,556.25 (2 contracts), area 07 at $13,157.14 (2 contracts), area 08 at $17,429.35 (4 contracts), area 10 at $14,865.00 (1 contract), area 12 at $15,998.80 (1 contract).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0425: 0425 5 Manhole, Adjust ($1,119.50 per EA, 80 contracts); 0425 6 Valve Boxes, Adjust ($983.70 per EA, 53 contracts); 0425 5 1 Manhole, Adjust, Utilities ($1,452.45 per EA, 41 contracts); 0425 1351 Inlets, Curb, Type P-5, <10' ($9,463.26 per EA, 38 contracts); 0425 1521 Inlets, DT BOT, Type C,<10' ($6,260.63 per EA, 38 contracts).
Related items in section 0425
- 0425 5 · Manhole, Adjust ($1,119.50/EA)
- 0425 6 · Valve Boxes, Adjust ($983.70/EA)
- 0425 5 1 · Manhole, Adjust, Utilities ($1,452.45/EA)
- 0425 1351 · Inlets, Curb, Type P-5, <10' ($9,463.26/EA)
- 0425 1521 · Inlets, DT BOT, Type C,<10' ($6,260.63/EA)
- 0425 1541 · Inlets, DT BOT, Type D, <10' ($7,311.31/EA)
- 0425 2 61 · Manholes, P-8, <10' ($7,273.90/EA)
- 0425 2 41 · Manholes, P-7, <10' ($7,512.23/EA)