Inlets, Curb, Type P-5, Partial (Item 0425 1355): FDOT Unit Price History
12 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $8,209.31/EA
- Contracts (12 mo)
- 12
- Total quantity (12 mo)
- 41 EA
- Total amount (12 mo)
- $336,582
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 21 | $8,789.50 | 48 | $421,896 |
| 2025 | 2025-01-01 – 2025-12-31 | 13 | $8,822.75 | 17 | $149,987 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 12 | $8,209.31 | 41 | $336,582 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 05 | 2 | $6,913.78 | -15.8% | 2 |
| 06 | 1 | $12,500.00 | +52.3% | 2 |
| 08 | 5 | $7,884.62 | -4% | 26 |
| 10 | 1 | $8,670.00 | +5.6% | 6 |
| 13 | 3 | $8,146.80 | -0.8% | 5 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0425 1355 (Inlets, Curb, Type P-5, Partial) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 12 contracts with a quantity-weighted average of $8,209.31 per EA, on 41 EA worth $336,582 in total.
The same report run for earlier periods shows $8,789.50 in 2024 (21 contracts, 48 EA), $8,822.75 in 2025 (13 contracts, 17 EA), $8,209.31 in the latest 12 months (12 contracts, 41 EA). From 2024 to the latest 12 months the weighted average fell 6.6%.
In the same 12 months, 5 of FDOT's 14 market areas reported this item: area 05 at $6,913.78 (2 contracts), area 06 at $12,500.00 (1 contract), area 08 at $7,884.62 (5 contracts), area 10 at $8,670.00 (1 contract), area 13 at $8,146.80 (3 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0425: 0425 5 Manhole, Adjust ($1,119.50 per EA, 80 contracts); 0425 6 Valve Boxes, Adjust ($983.70 per EA, 53 contracts); 0425 5 1 Manhole, Adjust, Utilities ($1,452.45 per EA, 41 contracts); 0425 1351 Inlets, Curb, Type P-5, <10' ($9,463.26 per EA, 38 contracts); 0425 1521 Inlets, DT BOT, Type C,<10' ($6,260.63 per EA, 38 contracts).
Related items in section 0425
- 0425 5 · Manhole, Adjust ($1,119.50/EA)
- 0425 6 · Valve Boxes, Adjust ($983.70/EA)
- 0425 5 1 · Manhole, Adjust, Utilities ($1,452.45/EA)
- 0425 1351 · Inlets, Curb, Type P-5, <10' ($9,463.26/EA)
- 0425 1521 · Inlets, DT BOT, Type C,<10' ($6,260.63/EA)
- 0425 1541 · Inlets, DT BOT, Type D, <10' ($7,311.31/EA)
- 0425 2 61 · Manholes, P-8, <10' ($7,273.90/EA)
- 0425 2 41 · Manholes, P-7, <10' ($7,512.23/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.