Inlets, Curb, Type P-3, <10' (Item 0425 1331): FDOT Unit Price History
12 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $11,474.29/EA
- Contracts (12 mo)
- 12
- Total quantity (12 mo)
- 64 EA
- Total amount (12 mo)
- $734,355
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 16 | $11,043.38 | 88 | $971,817 |
| 2025 | 2025-01-01 – 2025-12-31 | 11 | $12,602.52 | 17 | $214,243 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 12 | $11,474.29 | 64 | $734,355 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 1 | $8,375.00 | -27% | 2 |
| 05 | 1 | $7,750.00 | -32.5% | 1 |
| 06 | 1 | $11,383.00 | -0.8% | 1 |
| 07 | 2 | $8,025.00 | -30.1% | 24 |
| 08 | 3 | $11,725.45 | +2.2% | 4 |
| 09 | 1 | $15,789.67 | +37.6% | 15 |
| 12 | 1 | $12,150.00 | +5.9% | 14 |
| 13 | 2 | $17,341.67 | +51.1% | 3 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0425 1331 (Inlets, Curb, Type P-3, <10') is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 12 contracts with a quantity-weighted average of $11,474.29 per EA, on 64 EA worth $734,355 in total.
The same report run for earlier periods shows $11,043.38 in 2024 (16 contracts, 88 EA), $12,602.52 in 2025 (11 contracts, 17 EA), $11,474.29 in the latest 12 months (12 contracts, 64 EA). From 2024 to the latest 12 months the weighted average rose 3.9%.
Quantity let statewide shrank 27% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 8 of FDOT's 14 market areas reported this item: area 01 at $8,375.00 (1 contract), area 05 at $7,750.00 (1 contract), area 06 at $11,383.00 (1 contract), area 07 at $8,025.00 (2 contracts), area 08 at $11,725.45 (3 contracts), area 09 at $15,789.67 (1 contract), area 12 at $12,150.00 (1 contract), area 13 at $17,341.67 (2 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0425: 0425 5 Manhole, Adjust ($1,119.50 per EA, 80 contracts); 0425 6 Valve Boxes, Adjust ($983.70 per EA, 53 contracts); 0425 5 1 Manhole, Adjust, Utilities ($1,452.45 per EA, 41 contracts); 0425 1351 Inlets, Curb, Type P-5, <10' ($9,463.26 per EA, 38 contracts); 0425 1521 Inlets, DT BOT, Type C,<10' ($6,260.63 per EA, 38 contracts).
Related items in section 0425
- 0425 5 · Manhole, Adjust ($1,119.50/EA)
- 0425 6 · Valve Boxes, Adjust ($983.70/EA)
- 0425 5 1 · Manhole, Adjust, Utilities ($1,452.45/EA)
- 0425 1351 · Inlets, Curb, Type P-5, <10' ($9,463.26/EA)
- 0425 1521 · Inlets, DT BOT, Type C,<10' ($6,260.63/EA)
- 0425 1541 · Inlets, DT BOT, Type D, <10' ($7,311.31/EA)
- 0425 2 61 · Manholes, P-8, <10' ($7,273.90/EA)
- 0425 2 41 · Manholes, P-7, <10' ($7,512.23/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.