Inlets, Curb, Type P-1, <10' (Item 0425 1311): FDOT Unit Price History
19 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $9,452.84/EA
- Contracts (12 mo)
- 19
- Total quantity (12 mo)
- 231 EA
- Total amount (12 mo)
- $2,183,606
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 21 | $11,273.83 | 117 | $1,319,038 |
| 2025 | 2025-01-01 – 2025-12-31 | 25 | $10,487.42 | 214 | $2,244,307 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 19 | $9,452.84 | 231 | $2,183,606 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 2 | $9,070.73 | -4% | 31 |
| 03 | 2 | $7,944.18 | -16% | 26 |
| 05 | 3 | $10,161.90 | +7.5% | 21 |
| 07 | 2 | $8,442.31 | -10.7% | 65 |
| 08 | 6 | $11,059.19 | +17% | 46 |
| 10 | 1 | $12,155.00 | +28.6% | 8 |
| 11 | 1 | $8,390.00 | -11.2% | 17 |
| 12 | 1 | $9,559.24 | +1.1% | 1 |
| 13 | 1 | $10,972.65 | +16.1% | 16 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0425 1311 (Inlets, Curb, Type P-1, <10') is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 19 contracts with a quantity-weighted average of $9,452.84 per EA, on 231 EA worth $2,183,606 in total.
The same report run for earlier periods shows $11,273.83 in 2024 (21 contracts, 117 EA), $10,487.42 in 2025 (25 contracts, 214 EA), $9,452.84 in the latest 12 months (19 contracts, 231 EA). From 2024 to the latest 12 months the weighted average fell 16.2%.
Quantity let statewide grew 97% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 9 of FDOT's 14 market areas reported this item: area 01 at $9,070.73 (2 contracts), area 03 at $7,944.18 (2 contracts), area 05 at $10,161.90 (3 contracts), area 07 at $8,442.31 (2 contracts), area 08 at $11,059.19 (6 contracts), area 10 at $12,155.00 (1 contract), area 11 at $8,390.00 (1 contract), area 12 at $9,559.24 (1 contract), area 13 at $10,972.65 (1 contract).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0425: 0425 5 Manhole, Adjust ($1,119.50 per EA, 80 contracts); 0425 6 Valve Boxes, Adjust ($983.70 per EA, 53 contracts); 0425 5 1 Manhole, Adjust, Utilities ($1,452.45 per EA, 41 contracts); 0425 1351 Inlets, Curb, Type P-5, <10' ($9,463.26 per EA, 38 contracts); 0425 1521 Inlets, DT BOT, Type C,<10' ($6,260.63 per EA, 38 contracts).
Related items in section 0425
- 0425 5 · Manhole, Adjust ($1,119.50/EA)
- 0425 6 · Valve Boxes, Adjust ($983.70/EA)
- 0425 5 1 · Manhole, Adjust, Utilities ($1,452.45/EA)
- 0425 1351 · Inlets, Curb, Type P-5, <10' ($9,463.26/EA)
- 0425 1521 · Inlets, DT BOT, Type C,<10' ($6,260.63/EA)
- 0425 1541 · Inlets, DT BOT, Type D, <10' ($7,311.31/EA)
- 0425 2 61 · Manholes, P-8, <10' ($7,273.90/EA)
- 0425 2 41 · Manholes, P-7, <10' ($7,512.23/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.