Cracks Inject & Seal- Structures Rehab (Item 0411 2): FDOT Unit Price History
12 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF
- Weighted average (12 mo)
- $129.55/LF
- Contracts (12 mo)
- 12
- Total quantity (12 mo)
- 3,252 LF
- Total amount (12 mo)
- $421,308
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 11 | $205.26 | 1,388 | $284,900 |
| 2025 | 2025-01-01 – 2025-12-31 | 20 | $110.71 | 10,980 | $1,215,598 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 12 | $129.55 | 3,252 | $421,308 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 3 | $129.94 | +0.3% | 1,614 |
| 07 | 2 | $367.71 | +183.8% | 61 |
| 08 | 1 | $500.00 | +286% | 27 |
| 12 | 4 | $143.19 | +10.5% | 985 |
| 14 | 1 | $91.00 | -29.8% | 265 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0411 2 (Cracks Inject & Seal- Structures Rehab) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 12 contracts with a quantity-weighted average of $129.55 per LF, on 3,252 LF worth $421,308 in total.
The same report run for earlier periods shows $205.26 in 2024 (11 contracts, 1,388 LF), $110.71 in 2025 (20 contracts, 10,980 LF), $129.55 in the latest 12 months (12 contracts, 3,252 LF). From 2024 to the latest 12 months the weighted average fell 36.9%.
Quantity let statewide grew 134% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 5 of FDOT's 14 market areas reported this item: area 01 at $129.94 (3 contracts), area 07 at $367.71 (2 contracts), area 08 at $500.00 (1 contract), area 12 at $143.19 (4 contracts), area 14 at $91.00 (1 contract).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0411: 0411 1 Epoxy Material FOR Crack Injection- Structures Rehab ($318.55 per GA, 12 contracts).
Related items in section 0411
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.