Epoxy Material FOR Crack Injection- Structures Rehab (Item 0411 1): FDOT Unit Price History

12 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure GA

Weighted average (12 mo)
$318.55/GA
Contracts (12 mo)
12
Total quantity (12 mo)
93 GA
Total amount (12 mo)
$29,625

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-3111$789.75105$82,924
20252025-01-01 – 2025-12-3120$290.72864$251,185
Latest 12 months2025-11-01 – 2026-10-3112$318.5593$29,625

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
013$224.35-29.6%42
072$299.68-5.9%6
081$100.00-68.6%1
124$465.33+46.1%30
141$405.00+27.1%8

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0411 1 (Epoxy Material FOR Crack Injection- Structures Rehab) is measured in GA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 12 contracts with a quantity-weighted average of $318.55 per GA, on 93 GA worth $29,625 in total.

The same report run for earlier periods shows $789.75 in 2024 (11 contracts, 105 GA), $290.72 in 2025 (20 contracts, 864 GA), $318.55 in the latest 12 months (12 contracts, 93 GA). From 2024 to the latest 12 months the weighted average fell 59.7%.

In the same 12 months, 5 of FDOT's 14 market areas reported this item: area 01 at $224.35 (3 contracts), area 07 at $299.68 (2 contracts), area 08 at $100.00 (1 contract), area 12 at $465.33 (4 contracts), area 14 at $405.00 (1 contract).

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0411: 0411 2 Cracks Inject & Seal- Structures Rehab ($129.55 per LF, 12 contracts).

Related items in section 0411

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.