Milling Existing Asphalt Pavement, 2 3/4" AVG Depth (Item 0327 70 15): FDOT Unit Price History
19 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure SY
- Weighted average (12 mo)
- $2.00/SY
- Contracts (12 mo)
- 19
- Total quantity (12 mo)
- 1,755,828 SY
- Total amount (12 mo)
- $3,515,998
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 20 | $3.28 | 1,802,934 | $5,907,888 |
| 2025 | 2025-01-01 – 2025-12-31 | 17 | $3.48 | 506,124 | $1,762,560 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 19 | $2.00 | 1,755,828 | $3,515,998 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 1 | $3.48 | +74% | 1,135 |
| 04 | 2 | $1.90 | -5% | 357,895 |
| 05 | 3 | $1.34 | -33% | 440,026 |
| 06 | 1 | $3.25 | +62.5% | 392 |
| 07 | 3 | $1.66 | -17% | 313,902 |
| 08 | 5 | $2.19 | +9.5% | 417,620 |
| 09 | 1 | $3.50 | +75% | 220,126 |
| 12 | 2 | $3.71 | +85.5% | 3,974 |
| 13 | 1 | $20.00 | +900% | 758 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0327 70 15 (Milling Existing Asphalt Pavement, 2 3/4" AVG Depth) is measured in SY. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 19 contracts with a quantity-weighted average of $2.00 per SY, on 1,755,828 SY worth $3,515,998 in total.
The same report run for earlier periods shows $3.28 in 2024 (20 contracts, 1,802,934 SY), $3.48 in 2025 (17 contracts, 506,124 SY), $2.00 in the latest 12 months (19 contracts, 1,755,828 SY). From 2024 to the latest 12 months the weighted average fell 39.0%.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 3 market areas with at least three contracts, market area 05 had the lowest weighted average ($1.34 per SY, 3 contracts) and market area 08 the highest ($2.19, 5 contracts), 1.6 times as much. Market area 08 let the most contracts with this item (5). 9 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0327: 0327 70 6 Milling Existing Asphalt Pavement, 1 1/2" AVG Depth ($2.79 per SY, 173 contracts); 0327 70 4 Milling Existing Asphalt Pavement, 3" AVG Depth ($2.91 per SY, 73 contracts); 0327 70 5 Milling Existing Asphalt Pavement, 2" AVG Depth ($1.90 per SY, 52 contracts); 0327 70 11 Milling Existing Asphalt Pavement, 2 1/4" AVG Depth ($2.22 per SY, 46 contracts); 0327 70 19 Milling Existing Asphalt Pavement, 3/4" AVG Depth ($2.13 per SY, 31 contracts).
Related items in section 0327
- 0327 70 6 · Milling Existing Asphalt Pavement, 1 1/2" AVG Depth ($2.79/SY)
- 0327 70 4 · Milling Existing Asphalt Pavement, 3" AVG Depth ($2.91/SY)
- 0327 70 5 · Milling Existing Asphalt Pavement, 2" AVG Depth ($1.90/SY)
- 0327 70 11 · Milling Existing Asphalt Pavement, 2 1/4" AVG Depth ($2.22/SY)
- 0327 70 19 · Milling Existing Asphalt Pavement, 3/4" AVG Depth ($2.13/SY)
- 0327 70 2 · Milling Existing Asphalt Pavement, 3 1/2" AVG Depth ($3.26/SY)
- 0327 70 7 · Milling Existing Asphalt Pavement, 4" AVG Depth ($3.29/SY)
- 0327 70 1 · Milling Existing Asphalt Pavement, 1" AVG Depth ($2.18/SY)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.