Regular Excavation (Item 0120 1): FDOT Unit Price History
142 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure CY
- Weighted average (12 mo)
- $7.20/CY
- Contracts (12 mo)
- 142
- Total quantity (12 mo)
- 4,249,232.7 CY
- Total amount (12 mo)
- $30,591,265
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 186 | $14.91 | 2,617,877.3 | $39,020,455 |
| 2025 | 2025-01-01 – 2025-12-31 | 166 | $9.32 | 5,621,706.1 | $52,403,225 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 142 | $7.20 | 4,249,232.7 | $30,591,265 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 11 | $11.02 | +53.1% | 196,518.2 |
| 02 | 9 | $15.40 | +113.9% | 25,655.2 |
| 03 | 7 | $6.90 | -4.2% | 205,116.6 |
| 04 | 10 | $39.63 | +450.4% | 6,492.5 |
| 05 | 7 | $18.64 | +158.9% | 34,341.8 |
| 06 | 13 | $5.55 | -22.9% | 181,309.6 |
| 07 | 17 | $4.13 | -42.6% | 2,267,604.6 |
| 08 | 31 | $5.77 | -19.9% | 555,075.6 |
| 09 | 6 | $28.25 | +292.4% | 7,346.1 |
| 10 | 11 | $19.79 | +174.9% | 42,954.5 |
| 11 | 2 | $14.01 | +94.6% | 43,993.1 |
| 12 | 12 | $14.48 | +101.1% | 648,542.9 |
| 13 | 5 | $33.04 | +358.9% | 30,936.8 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0120 1 (Regular Excavation) is measured in CY. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 142 contracts with a quantity-weighted average of $7.20 per CY, on 4,249,232.7 CY worth $30,591,265 in total.
The same report run for earlier periods shows $14.91 in 2024 (186 contracts, 2,617,877.3 CY), $9.32 in 2025 (166 contracts, 5,621,706.1 CY), $7.20 in the latest 12 months (142 contracts, 4,249,232.7 CY). From 2024 to the latest 12 months the weighted average fell 51.7%.
Quantity let statewide grew 62% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 12 market areas with at least three contracts, market area 07 had the lowest weighted average ($4.13 per CY, 17 contracts) and market area 04 the highest ($39.63, 10 contracts), 9.6 times as much. Market area 08 let the most contracts with this item (31). 13 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0120: 0120 6 Embankment ($10.46 per CY, 127 contracts); 0120 2 2 Borrow Excavation, Truck Measure ($40.45 per CY, 55 contracts); 0120 71 Regular Excavation (3-R Projects Only) ($32,244.84 per LS, 38 contracts); 0120 4 Subsoil Excavation ($12.74 per CY, 35 contracts); 0120 5 Channel Excavation ($7.06 per CY, 3 contracts).
Related items in section 0120
- 0120 6 · Embankment ($10.46/CY)
- 0120 2 2 · Borrow Excavation, Truck Measure ($40.45/CY)
- 0120 71 · Regular Excavation (3-R Projects Only) ($32,244.84/LS)
- 0120 4 · Subsoil Excavation ($12.74/CY)
- 0120 5 · Channel Excavation ($7.06/CY)
- 0120 6 11 · Embankment, Supplied BY Department, Delivered BY Department ($4.15/CY)
- 0120 6 12 · Embankment, Supplied BY Department, Delivered BY Contractor ($9.35/CY)
- 0120 74 · Surcharge Embankment ($8.50/CY)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.