Square G, Inc.: TxDOT Bid Results and Margins

Name as published by TxDOT: SQUARE G, INC. · Data as published by TxDOT, lettings Jan 16, 2025 to May 7, 2026, retrieved Nov 24, 2026.

Proposals bid
11
Low bids (rank 1)
2
Win rate
18.18%
Low-bid value
$1.1M
Money left on table
$90K
Avg. bid vs. estimate
-9.26%

From Jan 16, 2025 to May 7, 2026, Square G, Inc. submitted 11 bids on TxDOT proposals and was the apparent low bidder on 2 of them (18.18%), with low bids totalling $1,086,441. In 2 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $90,251 (8.31% of those bids); the median gap was 7.81%. On average its bids came in 9.26% below TxDOT's engineer's estimate. Its most frequent district was Amarillo (3 bids).

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

By year

YearBidsLow bidsWin rateLow-bid value
2025800.0%$0
20263266.7%$1,086,441

Head-to-head rivals

BidderProposals togetherRanked ahead
Abescape Group LLC63 of 6
T&l Cleaning Services LLC66 of 6
R&m Incorporated53 of 5
Cehand Services LLC44 of 4
Texas Blacktops LLC43 of 4
Cross Plus Construction, LLC33 of 3
Light & Foliage Supply, LLC33 of 3
Lukeda Sandblasting & Services LLC30 of 3

Districts and work types

DistrictBids
Amarillo3
San Angelo3
Brownwood2
Paris2
Childress1
Work type of low bidsLow bids
Routine Maintenance Project2

Closest second-place finishes

Let dateProposalCountyLow bidderLow bidThis bidvs. low bid
2025-10-156490-48-001McCullochDiamond I Services, LLC$339,149$341,550+0.7%
2025-10-026486-06-001Tom GreenYanacek Irrigation$186,000$192,061+3.3%
2026-05-076500-23-001HemphillBert Whitaker$708,982$749,490+5.7%

Recent bids

Let dateProposalCountyWork typeRankBid totalvs. low bidvs. estimate
2026-05-076500-23-001HemphillRoutine Maintenance Project2 of 6$749,490+5.7%+4.5%
2026-05-076500-26-001MooreRoutine Maintenance Project1 of 6$521,111—+3.9%
2026-05-076500-27-001HutchinsonRoutine Maintenance Project1 of 6$565,330—-12%
2025-10-156490-48-001McCullochRoutine Maintenance Project2 of 5$341,550+0.7%-23.6%
2025-10-156490-52-001San SabaRoutine Maintenance Project3 of 5$316,264+12.2%-23.6%
2025-10-026486-06-001Tom GreenRoutine Maintenance Project - Sealed2 of 6$192,061+3.3%+2.6%
2025-08-216479-46-001CrockettRoutine Maintenance Project - Sealed3 of 8$228,253+63.9%-13.7%
2025-08-216479-47-001SuttonRoutine Maintenance Project - Sealed4 of 7$332,329+41.5%-17.1%
2025-04-166473-81-001HardemanRoutine Maintenance Project - Sealed5 of 6$960,768+10.3%-1.9%
2025-02-206475-18-001Red RiverRoutine Maintenance Project - Sealed4 of 6$319,467+14.3%-7.3%
2025-01-166475-16-001LamarRoutine Maintenance Project - Sealed3 of 6$328,665+4.1%-13.6%

Report an error. Wrong company merged, a name change, or a figure that does not match TxDOT's file? Email bidtabulation@apps.adeptaoperations.com. We respond within five business days. See how corrections work.

Compare your own unit prices with TxDOT history: benchmark a bid tab.