Name as published by TxDOT: Rucoba & Maya Construction, LLC · Data as published by TxDOT, lettings Feb 5, 2026 to Nov 4, 2026, retrieved Nov 24, 2026.

Proposals bid
9
Low bids (rank 1)
3
Win rate
33.33%
Low-bid value
$10.4M
Money left on table
$416K
Avg. bid vs. estimate
+14.31%

From Feb 5, 2026 to Nov 4, 2026, Rucoba & Maya Construction, LLC submitted 9 bids on TxDOT proposals and was the apparent low bidder on 3 of them (33.33%), with low bids totalling $10,420,902. In 3 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $416,086 (3.99% of those bids); the median gap was 3.87%. On average its bids came in 14.31% above TxDOT's engineer's estimate. Its most frequent district was Yoakum (4 bids).

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

By year

YearBidsLow bidsWin rateLow-bid value
20269333.3%$10,420,902

Head-to-head rivals

BidderProposals togetherRanked ahead
Stx Civil95 of 9
E-Z Bel Construction, LLC63 of 6
Texas Steel Industrial Placing, LLC62 of 6
Hodges and Son Construction Company, Inc.41 of 4
Joe Bland Construction LLC43 of 4
Presidio Contracting, LLC41 of 4
Trevway, Inc.41 of 4
Castillo Aranda LLC32 of 3

Districts and work types

DistrictBids
Yoakum4
Austin2
Bryan1
San Antonio1
Waco1
Work type of low bidsLow bids
Bridge Replacement1
Pedestrian, Sidewalks & Curb Ramps1
Rehabilitation of Existing Road1

Recent bids

Let dateProposalCountyWork typeRankBid totalvs. low bidvs. estimate
2026-11-040285-03-066HaysPedestrian, Sidewalks & Curb Ramps3 of 9$1,103,755+16.1%+17.5%
2026-11-030917-30-068BurlesonBridge Replacement13 of 15$954,437+32.2%+34%
2026-09-020913-09-134WhartonBridge Replacement1 of 12$2,677,071—+14.2%
2026-08-063534-01-021BellPedestrian, Sidewalks & Curb Ramps1 of 8$4,094,515—-8.3%
2026-08-050913-28-101FayetteBridge Replacement5 of 9$1,988,206+22.9%+16.3%
2026-07-020266-04-053ColoradoSafety Improvement Projects5 of 9$6,413,924+34.2%+23.3%
2026-07-010211-10-053ColoradoPedestrian, Sidewalks & Curb Ramps8 of 10$1,869,911+14.7%+7.4%
2026-05-071271-01-013WilsonBridge Replacement17 of 17$1,659,957+74.9%+38%
2026-02-051201-02-026WilliamsonRehabilitation of Existing Road1 of 10$3,649,316—-13.6%