Skip to content
BidTabulation.comDOT bid tabulations & unit-price intelligence
Menu

Pmi Pavement Marking, LLC: TxDOT Bid Results and Margins

Name as published by TxDOT: PMI PAVEMENT MARKING, LLC · Data as published by TxDOT, lettings Dec 4, 2024 to Oct 7, 2026, retrieved Nov 24, 2026.

Proposals bid
17
Low bids (rank 1)
2
Win rate
11.76%
Low-bid value
$707K
Money left on table
$24K
Avg. bid vs. estimate
-1.42%

From Dec 4, 2024 to Oct 7, 2026, Pmi Pavement Marking, LLC submitted 17 bids on TxDOT proposals and was the apparent low bidder on 2 of them (11.76%), with low bids totalling $707,104. In 2 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $23,947 (3.39% of those bids); the median gap was 2.46%. On average its bids came in 1.42% below TxDOT's engineer's estimate. Its most frequent district was Odessa (7 bids).

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

By year

YearBidsLow bidsWin rateLow-bid value
2024100.0%$0
20251100.0%$0
20265240.0%$707,104

Head-to-head rivals

BidderProposals togetherRanked ahead
Trp Infrastructure Services, LLC1711 of 17
L&l Company145 of 14
Stripe-A-Zone, LLC93 of 9
Vizcaino, L.P.92 of 9
Centerline Technologies, LLC71 of 7
The Confidence Group, Inc63 of 6
Grey Sky Construction LLC54 of 5
Pavement Markings Inc.54 of 5

Districts and work types

DistrictBids
Odessa7
Lubbock4
El Paso2
Laredo2
San Angelo1
Work type of low bidsLow bids
Routine Maintenance Project2

Closest second-place finishes

Let dateProposalCountyLow bidderLow bidThis bidvs. low bid
2025-04-086481-51-001MidlandVizcaino, L.P.$462,533$497,350+7.5%
2025-02-116477-24-001PecosL&l Company$242,300$262,050+8.2%
2024-12-040924-00-119El PasoCenterline Technologies, LLC$3,964,118$4,492,765+13.3%

Recent bids

Let dateProposalCountyWork typeRankBid totalvs. low bidvs. estimate
2026-10-070907-00-217Tom GreenTraffic Control Devices7 of 7$3,376,355+33%-2%
2026-07-010906-00-264EctorTraffic Control Devices7 of 8$7,599,052+38.5%+14.7%
2026-06-046497-64-001El PasoRoutine Maintenance Project1 of 2$500,077—-0.6%
2026-04-216497-99-001MidlandRoutine Maintenance Project1 of 13$207,027—-68.6%
2026-02-050905-00-127LubbockTraffic Control Devices5 of 10$7,396,318+14%-9.7%
2025-10-146490-54-001LubbockRoutine Maintenance Project - Sealed5 of 5$1,347,133+70.7%+42.9%
2025-08-080906-00-249EctorTraffic Control Devices4 of 8$3,069,645+5.9%-15.7%
2025-08-076479-53-001BellRoutine Maintenance Project7 of 11$3,319,796+24.8%-19.3%
2025-07-026483-93-001ZavalaRoutine Maintenance Project - Sealed4 of 5$1,012,168+57.8%-30.9%
2025-04-086481-51-001MidlandRoutine Maintenance Project2 of 6$497,350+7.5%+4.2%
2025-03-116477-23-001PecosRoutine Maintenance Project4 of 5$116,024+31.8%+46.5%
2025-03-116477-25-001EctorRoutine Maintenance Project3 of 7$412,150+4.8%-7.1%

Report an error. Wrong company merged, a name change, or a figure that does not match TxDOT's file? Email bidtabulation@apps.adeptaoperations.com. We respond within five business days. See how corrections work.