Fc Traffic Control, LLC: TxDOT Bid Results and Margins

Name as published by TxDOT: FC TRAFFIC CONTROL, LLC · Data as published by TxDOT, lettings Apr 9, 2026 to Nov 18, 2026, retrieved Nov 24, 2026.

Proposals bid
40
Low bids (rank 1)
15
Win rate
37.5%
Low-bid value
$14.3M
Money left on table
$2.1M
Avg. bid vs. estimate
+28.78%

From Apr 9, 2026 to Nov 18, 2026, Fc Traffic Control, LLC submitted 40 bids on TxDOT proposals and was the apparent low bidder on 15 of them (37.5%), with low bids totalling $14,295,705. In 11 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $2,140,760 (19.15% of those bids); the median gap was 16.19%. On average its bids came in 28.78% above TxDOT's engineer's estimate. Its most frequent district was Bryan (7 bids).

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

By year

YearBidsLow bidsWin rateLow-bid value
2026401537.5%$14,295,705

Head-to-head rivals

BidderProposals togetherRanked ahead
Awp Safety2012 of 20
Trp Infrastructure Services, LLC96 of 9
Stripe-A-Zone, LLC85 of 8
L&l Company72 of 7
Stripe Lines, Inc.76 of 7
Anthony Services50 of 5
Pavement Markings Inc.54 of 5
D. I. J. Construction, Inc.42 of 4

Districts and work types

DistrictBids
Bryan7
Dallas6
Tyler5
Lufkin4
Odessa4
Work type of low bidsLow bids
Routine Maintenance Project - Sealed14
Routine Maintenance Project1

Closest second-place finishes

Let dateProposalCountyLow bidderLow bidThis bidvs. low bid
2026-07-026503-33-001LamarAwp Safety$1,867,015$1,938,500+3.8%
2026-09-096501-34-001EllisAwp Safety$748,500$804,900+7.5%
2026-05-066500-75-001WalkerAwp Safety$3,004,120$3,245,800+8%
2026-07-020057-03-052FreestoneL&l Company$1,300,246$1,412,418+8.6%
2026-06-036497-46-001TarrantStripe-A-Zone, LLC$1,095,878$1,206,280+10.1%

Recent bids

Let dateProposalCountyWork typeRankBid totalvs. low bidvs. estimate
2026-11-186510-96-001BrazosRoutine Maintenance Project2 of 2$382,000+29.8%-1.1%
2026-11-106506-72-001HarrisRoutine Maintenance Project - Sealed3 of 3$2,717,250+254.8%+367.8%
2026-11-056510-79-001LambRoutine Maintenance Project - Sealed1 of 3$331,625—-36.1%
2026-11-056510-80-001HaleRoutine Maintenance Project - Sealed1 of 3$182,004—-63.4%
2026-11-046509-96-001HendersonRoutine Maintenance Project - Sealed3 of 4$1,636,100+34.4%+37.1%
2026-11-036508-86-001GreggRoutine Maintenance Project - Sealed4 of 4$2,011,000+46.6%+43.1%
2026-10-216510-35-001AngelinaRoutine Maintenance Project - Sealed2 of 2$420,000+24.1%+20.6%
2026-10-146502-60-001DentonRoutine Maintenance Project - Sealed3 of 3$1,072,700+41.6%+29.7%
2026-10-136508-38-001SmithRoutine Maintenance Project - Sealed2 of 3$1,197,000+11.2%+27.2%
2026-10-136508-42-001CherokeeRoutine Maintenance Project - Sealed2 of 3$1,221,000+17.5%+40.9%
2026-10-066504-70-001WoodRoutine Maintenance Project - Sealed1 of 2$2,735,000—+18.7%
2026-09-226500-89-001LavacaRoutine Maintenance Project - Sealed2 of 2$322,380+24.4%+17%

Report an error. Wrong company merged, a name change, or a figure that does not match TxDOT's file? Email bidtabulation@apps.adeptaoperations.com. We respond within five business days. See how corrections work.

Compare your own unit prices with TxDOT history: benchmark a bid tab.