Name as published by TxDOT: COASCAPE GROUP, LLC · Data as published by TxDOT, lettings Nov 12, 2025 to Jul 23, 2026, retrieved Nov 24, 2026.

Proposals bid
13
Low bids (rank 1)
1
Win rate
7.69%
Low-bid value
$720K
Money left on table
$12K
Avg. bid vs. estimate
+14.51%

From Nov 12, 2025 to Jul 23, 2026, Coascape Group, LLC submitted 13 bids on TxDOT proposals and was the apparent low bidder on 1 of them (7.69%), with low bids totalling $720,414. In 1 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $12,329 (1.71% of those bids); the median gap was 1.71%. On average its bids came in 14.51% above TxDOT's engineer's estimate. Its most frequent district was Paris (6 bids).

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

By year

YearBidsLow bidsWin rateLow-bid value
2025400.0%$0
20269111.1%$720,414

Head-to-head rivals

BidderProposals togetherRanked ahead
Anthony Services102 of 10
Abescape Group LLC90 of 9
Cehand Services LLC70 of 7
Jasco32 of 3
Ortega's Lawn and Landscaping, LLC31 of 3
T&l Cleaning Services LLC32 of 3
Eastgate Services20 of 2
Marlane Construction, LLC20 of 2

Districts and work types

DistrictBids
Paris6
Wichita Falls3
Dallas1
Fort Worth1
San Angelo1
Work type of low bidsLow bids
Routine Maintenance Project - Sealed1

Closest second-place finishes

Let dateProposalCountyLow bidderLow bidThis bidvs. low bid
2025-12-186493-52-001DeltaEastgate Services$198,965$226,694+13.9%

Recent bids

Let dateProposalCountyWork typeRankBid totalvs. low bidvs. estimate
2026-07-236485-05-001CokeRoutine Maintenance Project - Sealed4 of 5$227,664+36%+36.6%
2026-04-156496-17-001WiseRoutine Maintenance Project - Sealed1 of 7$720,414—-11.5%
2026-03-196495-21-001CookeRoutine Maintenance Project3 of 3$313,071+8.2%-0.2%
2026-02-256495-22-001MontagueRoutine Maintenance Project4 of 5$456,087+34.3%+19.5%
2026-02-256495-24-001WichitaRoutine Maintenance Project6 of 6$408,904+68.5%+34.8%
2026-02-196493-58-001HuntRoutine Maintenance Project - Sealed5 of 5$361,861+20.5%+7.5%
2026-02-196493-59-001RainsRoutine Maintenance Project - Sealed5 of 5$259,524+20%+11.9%
2026-01-156493-54-001FanninRoutine Maintenance Project - Sealed5 of 5$474,484+24.7%+18.5%
2026-01-156493-55-001GraysonRoutine Maintenance Project - Sealed7 of 7$455,364+31.4%+19.7%
2025-12-186493-50-001HopkinsRoutine Maintenance Project - Sealed4 of 4$419,171+39.8%+22.7%
2025-12-186493-52-001DeltaRoutine Maintenance Project - Sealed2 of 3$226,694+13.9%+2.9%
2025-11-126485-33-001DentonRoutine Maintenance Project - Sealed7 of 8$508,031+28.6%+2.3%

Report an error. Wrong company merged, a name change, or a figure that does not match TxDOT's file? Email bidtabulation@apps.adeptaoperations.com. We respond within five business days. See how corrections work.