Green-Colored Pavement Markings, Bike Lane (Item 0714 10): FDOT Unit Price History
19 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure SF
- Weighted average (12 mo)
- $9.01/SF
- Contracts (12 mo)
- 19
- Total quantity (12 mo)
- 49,096 SF
- Total amount (12 mo)
- $442,367
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 18 | $8.76 | 117,012 | $1,025,539 |
| 2025 | 2025-01-01 – 2025-12-31 | 28 | $8.94 | 107,090 | $957,291 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 19 | $9.01 | 49,096 | $442,367 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 05 | 1 | $13.50 | +49.8% | 727 |
| 06 | 1 | $9.99 | +10.9% | 566 |
| 08 | 4 | $8.19 | -9.1% | 7,955 |
| 11 | 1 | $16.00 | +77.6% | 1,402 |
| 12 | 8 | $8.38 | -7% | 30,368 |
| 13 | 3 | $13.33 | +47.9% | 2,962 |
| 14 | 1 | $8.85 | -1.8% | 5,116 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0714 10 (Green-Colored Pavement Markings, Bike Lane) is measured in SF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 19 contracts with a quantity-weighted average of $9.01 per SF, on 49,096 SF worth $442,367 in total.
The same report run for earlier periods shows $8.76 in 2024 (18 contracts, 117,012 SF), $8.94 in 2025 (28 contracts, 107,090 SF), $9.01 in the latest 12 months (19 contracts, 49,096 SF). Across those periods the weighted average stayed within three percent.
Quantity let statewide shrank 58% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 3 market areas with at least three contracts, market area 08 had the lowest weighted average ($8.19 per SF, 4 contracts) and market area 13 the highest ($13.33, 3 contracts), 1.6 times as much. Market area 12 let the most contracts with this item (8). 7 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.