Permanent Tape, White, 3-9 Dotted, 6" Wide, FOR Concrete Surfaces (Item 0713103171): FDOT Unit Price History
12 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure GM
- Weighted average (12 mo)
- $15,707.94/GM
- Contracts (12 mo)
- 12
- Total quantity (12 mo)
- 2.12 GM
- Total amount (12 mo)
- $33,222
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 3 | $12,126.69 | 0.76 | $9,156 |
| 2025 | 2025-01-01 – 2025-12-31 | 19 | $10,654.60 | 4.63 | $49,352 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 12 | $15,707.94 | 2.12 | $33,222 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 03 | 1 | $27,618.98 | +75.8% | 0.09 |
| 04 | 1 | $22,539.19 | +43.5% | 0.11 |
| 05 | 3 | $14,574.47 | -7.2% | 0.94 |
| 06 | 2 | $10,823.49 | -31.1% | 0.81 |
| 07 | 1 | $24,000.00 | +52.8% | 0.04 |
| 08 | 1 | $7,037.04 | -55.2% | 0.03 |
| 12 | 2 | $65,875.76 | +319.4% | 0.07 |
| 13 | 1 | $8,256.06 | -47.4% | 0.03 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0713103171 (Permanent Tape, White, 3-9 Dotted, 6" Wide, FOR Concrete Surfaces) is measured in GM. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 12 contracts with a quantity-weighted average of $15,707.94 per GM, on 2.12 GM worth $33,222 in total.
The same report run for earlier periods shows $12,126.69 in 2024 (3 contracts, 0.76 GM), $10,654.60 in 2025 (19 contracts, 4.63 GM), $15,707.94 in the latest 12 months (12 contracts, 2.12 GM). From 2024 to the latest 12 months the weighted average rose 29.5%.
Quantity let statewide grew 179% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 8 of FDOT's 14 market areas reported this item: area 03 at $27,618.98 (1 contract), area 04 at $22,539.19 (1 contract), area 05 at $14,574.47 (3 contracts), area 06 at $10,823.49 (2 contracts), area 07 at $24,000.00 (1 contract), area 08 at $7,037.04 (1 contract), area 12 at $65,875.76 (2 contracts), area 13 at $8,256.06 (1 contract).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.