Tubular Marker, 36" White Post (Item 0704 1 3): FDOT Unit Price History
35 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $178.12/EA
- Contracts (12 mo)
- 35
- Total quantity (12 mo)
- 1,277 EA
- Total amount (12 mo)
- $227,458
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 16 | $195.81 | 178 | $34,854 |
| 2025 | 2025-01-01 – 2025-12-31 | 43 | $201.16 | 15,199 | $3,057,359 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 35 | $178.12 | 1,277 | $227,458 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 2 | $208.34 | +17% | 7 |
| 03 | 1 | $158.00 | -11.3% | 35 |
| 04 | 1 | $120.00 | -32.6% | 75 |
| 05 | 5 | $214.87 | +20.6% | 83 |
| 06 | 1 | $200.00 | +12.3% | 8 |
| 07 | 5 | $185.28 | +4% | 98 |
| 08 | 11 | $185.51 | +4.1% | 830 |
| 09 | 1 | $104.77 | -41.2% | 14 |
| 10 | 4 | $195.11 | +9.5% | 19 |
| 12 | 1 | $207.94 | +16.7% | 21 |
| 13 | 2 | $116.00 | -34.9% | 66 |
| 14 | 1 | $129.00 | -27.6% | 21 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0704 1 3 (Tubular Marker, 36" White Post) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 35 contracts with a quantity-weighted average of $178.12 per EA, on 1,277 EA worth $227,458 in total.
The same report run for earlier periods shows $195.81 in 2024 (16 contracts, 178 EA), $201.16 in 2025 (43 contracts, 15,199 EA), $178.12 in the latest 12 months (35 contracts, 1,277 EA). From 2024 to the latest 12 months the weighted average fell 9.0%.
Quantity let statewide grew 617% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 4 market areas with at least three contracts, market area 07 had the lowest weighted average ($185.28 per EA, 5 contracts) and market area 05 the highest ($214.87, 5 contracts), 1.2 times as much. Market area 08 let the most contracts with this item (11). 12 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0704: 0704 1 4 Tubular Marker, 36" Yellow Post ($175.00 per EA, 64 contracts).
Related items in section 0704
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.