Enhanced Highway Sign Assembly, AC Powered, F&I Ground Mount, Highlighted Sign <12 SF (Item 0700141140): FDOT Unit Price History
11 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $7,960.01/EA
- Contracts (12 mo)
- 11
- Total quantity (12 mo)
- 106 EA
- Total amount (12 mo)
- $843,761
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 10 | $8,548.15 | 148 | $1,265,126 |
| 2025 | 2025-01-01 – 2025-12-31 | 17 | $8,281.80 | 319 | $2,641,894 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 11 | $7,960.01 | 106 | $843,761 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 03 | 1 | $10,622.61 | +33.4% | 14 |
| 05 | 2 | $7,710.77 | -3.1% | 28 |
| 06 | 2 | $9,508.00 | +19.4% | 8 |
| 08 | 4 | $7,626.53 | -4.2% | 37 |
| 12 | 2 | $6,363.01 | -20.1% | 19 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0700141140 (Enhanced Highway Sign Assembly, AC Powered, F&I Ground Mount, Highlighted Sign <12 SF) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 11 contracts with a quantity-weighted average of $7,960.01 per EA, on 106 EA worth $843,761 in total.
The same report run for earlier periods shows $8,548.15 in 2024 (10 contracts, 148 EA), $8,281.80 in 2025 (17 contracts, 319 EA), $7,960.01 in the latest 12 months (11 contracts, 106 EA). From 2024 to the latest 12 months the weighted average fell 6.9%.
Quantity let statewide shrank 28% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 5 of FDOT's 14 market areas reported this item: area 03 at $10,622.61 (1 contract), area 05 at $7,710.77 (2 contracts), area 06 at $9,508.00 (2 contracts), area 08 at $7,626.53 (4 contracts), area 12 at $6,363.01 (2 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.