Pedestrian Signal, Remove PED Signal- Pole/Pedestal TO Remain (Item 0653 1 60): FDOT Unit Price History
42 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure AS
- Weighted average (12 mo)
- $198.52/AS
- Contracts (12 mo)
- 42
- Total quantity (12 mo)
- 319 AS
- Total amount (12 mo)
- $63,328
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 84 | $203.84 | 1,033 | $210,571 |
| 2025 | 2025-01-01 – 2025-12-31 | 52 | $224.07 | 426 | $95,454 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 42 | $198.52 | 319 | $63,328 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 03 | 2 | $201.20 | +1.3% | 10 |
| 04 | 2 | $267.07 | +34.5% | 6 |
| 05 | 4 | $234.41 | +18.1% | 32 |
| 06 | 4 | $178.84 | -9.9% | 49 |
| 07 | 1 | $193.50 | -2.5% | 1 |
| 08 | 9 | $213.72 | +7.7% | 61 |
| 10 | 3 | $172.23 | -13.2% | 21 |
| 11 | 2 | $212.77 | +7.2% | 18 |
| 12 | 6 | $181.55 | -8.5% | 34 |
| 13 | 9 | $190.80 | -3.9% | 87 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0653 1 60 (Pedestrian Signal, Remove PED Signal- Pole/Pedestal TO Remain) is measured in AS. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 42 contracts with a quantity-weighted average of $198.52 per AS, on 319 AS worth $63,328 in total.
The same report run for earlier periods shows $203.84 in 2024 (84 contracts, 1,033 AS), $224.07 in 2025 (52 contracts, 426 AS), $198.52 in the latest 12 months (42 contracts, 319 AS). Across those periods the weighted average stayed within three percent.
Quantity let statewide shrank 69% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 6 market areas with at least three contracts, market area 10 had the lowest weighted average ($172.23 per AS, 3 contracts) and market area 05 the highest ($234.41, 4 contracts), 1.4 times as much. Market area 08 let the most contracts with this item (9). 10 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0653: 0653 1 11 Pedestrian Signal, Furnish & Install LED Countdown, 1 WAY ($1,049.25 per AS, 98 contracts); 0653 1 12 Pedestrian Signal, Furnish & Install LED Countdown, 2 Ways ($1,915.66 per AS, 46 contracts); 0653 1 40 Pedestrian Signal, Relocate ($635.33 per AS, 1 contracts).
Related items in section 0653
- 0653 1 11 · Pedestrian Signal, Furnish & Install LED Countdown, 1 WAY ($1,049.25/AS)
- 0653 1 12 · Pedestrian Signal, Furnish & Install LED Countdown, 2 Ways ($1,915.66/AS)
- 0653 1 40 · Pedestrian Signal, Relocate ($635.33/AS)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.