Raised Rumble Strip SET- Permanent (Item 0546 71 1): FDOT Unit Price History
10 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $1,442.16/EA
- Contracts (12 mo)
- 10
- Total quantity (12 mo)
- 82 EA
- Total amount (12 mo)
- $118,257
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 10 | $1,173.15 | 90 | $105,584 |
| 2025 | 2025-01-01 – 2025-12-31 | 14 | $940.67 | 74 | $69,610 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 10 | $1,442.16 | 82 | $118,257 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 2 | $709.56 | -50.8% | 8 |
| 04 | 2 | $1,465.28 | +1.6% | 8 |
| 07 | 1 | $1,200.00 | -16.8% | 4 |
| 08 | 2 | $1,368.02 | -5.1% | 21 |
| 09 | 1 | $2,000.00 | +38.7% | 32 |
| 13 | 2 | $370.00 | -74.3% | 9 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0546 71 1 (Raised Rumble Strip SET- Permanent) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 10 contracts with a quantity-weighted average of $1,442.16 per EA, on 82 EA worth $118,257 in total.
The same report run for earlier periods shows $1,173.15 in 2024 (10 contracts, 90 EA), $940.67 in 2025 (14 contracts, 74 EA), $1,442.16 in the latest 12 months (10 contracts, 82 EA). From 2024 to the latest 12 months the weighted average rose 22.9%.
In the same 12 months, 6 of FDOT's 14 market areas reported this item: area 01 at $709.56 (2 contracts), area 04 at $1,465.28 (2 contracts), area 07 at $1,200.00 (1 contract), area 08 at $1,368.02 (2 contracts), area 09 at $2,000.00 (1 contract), area 13 at $370.00 (2 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0546: 0546 72 3 Ground-IN Rumble Strips, 8" Sinusoidal ($2,731.41 per GM, 62 contracts); 0546 72 1 Ground-IN Rumble Strips, 16" ($2,349.12 per GM, 24 contracts).
Related items in section 0546
- 0546 72 3 · Ground-IN Rumble Strips, 8" Sinusoidal ($2,731.41/GM)
- 0546 72 1 · Ground-IN Rumble Strips, 16" ($2,349.12/GM)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.