Concrete Barrier, With Junction Slab, 36" Single Slope (Item 0521 8 7): FDOT Unit Price History

13 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF

Weighted average (12 mo)
$471.42/LF
Contracts (12 mo)
13
Total quantity (12 mo)
47,447 LF
Total amount (12 mo)
$22,367,248

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-3112$461.5833,384$15,409,438
20252025-01-01 – 2025-12-3115$488.9848,382$23,657,860
Latest 12 months2025-11-01 – 2026-10-3113$471.4247,447$22,367,248

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
011$418.49-11.2%270
021$563.43+19.5%98
073$443.87-5.8%9,612
081$200.00-57.6%97
111$267.00-43.4%740
126$483.64+2.6%36,630

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0521 8 7 (Concrete Barrier, With Junction Slab, 36" Single Slope) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 13 contracts with a quantity-weighted average of $471.42 per LF, on 47,447 LF worth $22,367,248 in total.

The same report run for earlier periods shows $461.58 in 2024 (12 contracts, 33,384 LF), $488.98 in 2025 (15 contracts, 48,382 LF), $471.42 in the latest 12 months (13 contracts, 47,447 LF). Across those periods the weighted average stayed within three percent.

Quantity let statewide grew 42% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

In the same 12 months, 6 of FDOT's 14 market areas reported this item: area 01 at $418.49 (1 contract), area 02 at $563.43 (1 contract), area 07 at $443.87 (3 contracts), area 08 at $200.00 (1 contract), area 11 at $267.00 (1 contract), area 12 at $483.64 (6 contracts).

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0521: 0521 5 13 Concrete Traffic Railing- Bridge, 36" Single-Slope ($138.49 per LF, 23 contracts); 0521 72 40 Shoulder Concrete Barrier, 38" OR 44" Height ($350.56 per LF, 23 contracts); 0521 72 43 Shoulder Concrete Barrier, Curb AND Gutter Barrier ($327.83 per LF, 9 contracts); 0521 1 12 Median Concrete Barrier, Short Grade-Separated ($251.50 per LF, 8 contracts); 0521 1 14 Median Concrete Barrier, Variable Section Width FOR Sign OR Pier Shielding ($788.19 per LF, 7 contracts).

Related items in section 0521

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.