Bollards (Item 0519 78): FDOT Unit Price History

13 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA

Weighted average (12 mo)
$2,384.54/EA
Contracts (12 mo)
13
Total quantity (12 mo)
366 EA
Total amount (12 mo)
$872,740

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-3110$1,308.82181$236,896
20252025-01-01 – 2025-12-3110$2,953.03272$803,225
Latest 12 months2025-11-01 – 2026-10-3113$2,384.54366$872,740

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
062$3,941.43+65.3%21
072$2,275.00-4.6%48
085$899.82-62.3%169
101$4,700.00+97.1%6
112$4,123.97+72.9%121
131$1,500.00-37.1%1

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0519 78 (Bollards) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 13 contracts with a quantity-weighted average of $2,384.54 per EA, on 366 EA worth $872,740 in total.

The same report run for earlier periods shows $1,308.82 in 2024 (10 contracts, 181 EA), $2,953.03 in 2025 (10 contracts, 272 EA), $2,384.54 in the latest 12 months (13 contracts, 366 EA). From 2024 to the latest 12 months the weighted average rose 82.2%.

Quantity let statewide grew 102% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

In the same 12 months, 6 of FDOT's 14 market areas reported this item: area 06 at $3,941.43 (2 contracts), area 07 at $2,275.00 (2 contracts), area 08 at $899.82 (5 contracts), area 10 at $4,700.00 (1 contract), area 11 at $4,123.97 (2 contracts), area 13 at $1,500.00 (1 contract).

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.