Piles, Polyethylene Sheeting (Item 0459 71): FDOT Unit Price History

10 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure SY

Weighted average (12 mo)
$19.12/SY
Contracts (12 mo)
10
Total quantity (12 mo)
5,857 SY
Total amount (12 mo)
$111,996

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-316$18.285,640$103,084
20252025-01-01 – 2025-12-3112$24.379,072$221,071
Latest 12 months2025-11-01 – 2026-10-3110$19.125,857$111,996

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
011$10.00-47.7%122
031$450.00+2,253.6%107
073$5.61-70.7%3,964
081$9.00-52.9%174
101$20.00+4.6%158
111$43.00+124.9%339
122$21.22+11%993

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0459 71 (Piles, Polyethylene Sheeting) is measured in SY. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 10 contracts with a quantity-weighted average of $19.12 per SY, on 5,857 SY worth $111,996 in total.

The same report run for earlier periods shows $18.28 in 2024 (6 contracts, 5,640 SY), $24.37 in 2025 (12 contracts, 9,072 SY), $19.12 in the latest 12 months (10 contracts, 5,857 SY). From 2024 to the latest 12 months the weighted average rose 4.6%.

In the same 12 months, 7 of FDOT's 14 market areas reported this item: area 01 at $10.00 (1 contract), area 03 at $450.00 (1 contract), area 07 at $5.61 (3 contracts), area 08 at $9.00 (1 contract), area 10 at $20.00 (1 contract), area 11 at $43.00 (1 contract), area 12 at $21.22 (2 contracts).

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.