Sheet Piling Steel, Temporary-Critical (Item 0455133 2): FDOT Unit Price History

14 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure SF

Weighted average (12 mo)
$15.82/SF
Contracts (12 mo)
14
Total quantity (12 mo)
294,429 SF
Total amount (12 mo)
$4,657,609

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-317$33.33509,276$16,976,316
20252025-01-01 – 2025-12-3112$32.36445,626$14,418,595
Latest 12 months2025-11-01 – 2026-10-3114$15.82294,429$4,657,609

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
031$65.09+311.4%4,789
043$21.89+38.4%14,234
071$57.00+260.3%14,888
082$91.54+478.6%8,679
101$88.00+456.3%12,773
124$0.140-99.1%200,873
132$32.43+105%38,193

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0455133 2 (Sheet Piling Steel, Temporary-Critical) is measured in SF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 14 contracts with a quantity-weighted average of $15.82 per SF, on 294,429 SF worth $4,657,609 in total.

The same report run for earlier periods shows $33.33 in 2024 (7 contracts, 509,276 SF), $32.36 in 2025 (12 contracts, 445,626 SF), $15.82 in the latest 12 months (14 contracts, 294,429 SF). From 2024 to the latest 12 months the weighted average fell 52.5%.

Quantity let statewide shrank 42% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

In the same 12 months, 7 of FDOT's 14 market areas reported this item: area 03 at $65.09 (1 contract), area 04 at $21.89 (3 contracts), area 07 at $57.00 (1 contract), area 08 at $91.54 (2 contracts), area 10 at $88.00 (1 contract), area 12 at $0.140 (4 contracts), area 13 at $32.43 (2 contracts).

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.