Edgedrain Draincrete, Standard (Item 0446 1 1): FDOT Unit Price History
10 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF
- Weighted average (12 mo)
- $31.98/LF
- Contracts (12 mo)
- 10
- Total quantity (12 mo)
- 36,078 LF
- Total amount (12 mo)
- $1,153,661
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 10 | $42.05 | 60,297 | $2,535,522 |
| 2025 | 2025-01-01 – 2025-12-31 | 6 | $40.81 | 148,820 | $6,073,673 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 10 | $31.98 | 36,078 | $1,153,661 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 05 | 3 | $28.28 | -11.6% | 19,402 |
| 06 | 2 | $30.90 | -3.4% | 7,001 |
| 07 | 1 | $39.00 | +22% | 3,073 |
| 08 | 2 | $35.09 | +9.7% | 3,524 |
| 13 | 2 | $47.15 | +47.4% | 3,078 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0446 1 1 (Edgedrain Draincrete, Standard) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 10 contracts with a quantity-weighted average of $31.98 per LF, on 36,078 LF worth $1,153,661 in total.
The same report run for earlier periods shows $42.05 in 2024 (10 contracts, 60,297 LF), $40.81 in 2025 (6 contracts, 148,820 LF), $31.98 in the latest 12 months (10 contracts, 36,078 LF). From 2024 to the latest 12 months the weighted average fell 23.9%.
Quantity let statewide shrank 40% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 5 of FDOT's 14 market areas reported this item: area 05 at $28.28 (3 contracts), area 06 at $30.90 (2 contracts), area 07 at $39.00 (1 contract), area 08 at $35.09 (2 contracts), area 13 at $47.15 (2 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0446: 0446 71 1 Edgedrain Outlet Pipe, 4" ($63.05 per LF, 9 contracts).
Related items in section 0446
- 0446 71 1 · Edgedrain Outlet Pipe, 4" ($63.05/LF)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.